Basement Rough-in

Basement Mechanical

It’s been a long time coming (like most things in this project) but we’ve passed our rough plumbing inspection for the basement! We passed our electrical inspection a month and a half ago, but we’ve grown used to the plumbing going slowly. This phase of the project was frustrating because we couldn’t do much ourselves to speed the process along, and we kept running into issues. Fortunately, all of them have been resolved.

Bathroom rough-in
Bathroom rough-in

Our new water service is a 1½” copper line, whereas our old service was only ¾”. Because of that, when we installed our whole-house water filter a few years back, we ran ¾” pipe. The plumbers took out a lot of that line when they brought in the new service and started adding branches for the bathroom, including the connections for the water heater ( temporarily on the first floor) running mostly in 1″ before and after the filter. On top of that, when I went to hook the filter back up, I realized that the new curb in the basement was preventing the filter from sitting close enough to the wall to connect to the existing pipes, meaning I was going to have to reconfigure it anyway. I bought new, bigger, 1″ filter housings and asked the plumbers to re-plumb the remaining section so that everything would be 1″ (and to add back the water heater hookup while they were at it).

Filter re-installed
Filter re-installed

The plumbers seemed vexed by the filter setup and I had to have them come back and change it multiple times until it was correct. This added weeks to the process all by itself, on top of the generally slow work they’d been doing. Then they asked for their money, so I asked when it was going to get inspected. That took another couple of weeks to get the inspector out, but they finally wrapped up Thursday of last week.

The electrical work went quickly because a lot of it was already done last year, but there were a couple of additions and modifications. We had to redo the grounding strap because the water service moved to the front of the house, add outlets for the sump pump and ejector pit, and add the switches, lights, and outlets for the bathroom and other new interior walls. We still need Lester, our radiant contractor, to come back and connect the PEX lines in the slab and disconnect our radiators on the second floor, but that shouldn’t impact the rest of the work we’re doing.

We were gone all weekend, but now I’m finally back to work, with a new goal of getting us moved into the basement by August 20th, the fifth anniversary of us moving into the second floor. I think if we’re still living in the second floor more than five years into our “five-year project”, I’ll have to start considering arson. There’s a lot to do, starting with the venting for the bath fan, leveling the bathroom ceiling, and a few other minor tasks. That will be followed by drywall and tiling, the temporary walls, and the bathroom fixtures.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Scroll to top