Page 35 of 59

On the Level

Before we bought our extreme fixer upper, we watched a lot of Holmes on Homes. In addition to an irrational fear of hiring contractors, the show also instilled the importance of building level, plumb, and true. When you’re renovating an old house that’s something of an uphill battle, and at times it’s downright impossible. However, we’re planning on in-floor radiant heat, which uses plywood and aluminum panels that lie on top of the subfloor and has channels for PEX tubing. The subfloor needed to be level and flat, and the existing plank floor was not going to cut it.

Wet wall subfloor

Wet wall subfloor

The first new subfloor was done when I reframed the wet wall back in September. At the time I decided that “level” was where the joists rested on the steel beam at the center of the house, since I knew the beam was level. The joists sloped slightly higher toward the South wall, so I used a planer to shave them down to be level and put the new subfloor down. I call this planing method of leveling “Method One”.

Shimming over subfloor

Shimming over subfloor

When I started work on the back section of subfloor, I realized that the wet wall was the exception rather than the rule when it came to joist height at the South wall. Most joists were ¾” higher at the outside wall than the beam, making Method One a bad option. Not only would planing that much off be a time consuming pain, I didn’t like removing that much wood from the joists. I decided instead to establish a new level, on top of the small section of subfloor I’d already done. Instead of planing down, I cut and glued down long shims that tapered from nothing to ¾” (depending on the particular joist) over the course of ten feet. This is “Method Two”. It is also a pain in the ass, but slightly less so. There were a few variations of this while we tried to work out the best way to do it.

Jacking up joists

Jacking up joists

With the back section leveled, but time consumingly so, I wanted to find a faster way to do it. Since the ¾” slope was fairly consistent, I next tried jacking up each joist at the beam and/or the outside wall and putting a shim underneath it, using my trusty hydraulic jack. This is “Method Three” and so far the most straightforward, if still time consuming. In some cases this was all I needed to do, while in others there was still a bow in the center of the spans that I fixed with a long shim, ala Method Two.

I did consider some other methods, such as sistering another joist to the first one. Some people have even used just a 2×4 rather than a full height piece. I didn’t do that partly because I didn’t want to rip out and replace all of the cross bracing between the joists, plus I don’t like the idea of the weight being carried off center of the joist. I want the floor to be as quiet as possible, which is why all the shims and subfloor are being glued down in addition to screws.

Shimming under the joist

Shimming under the joist

I still have a ways to go before the subfloor is done. I’m doing the leveling and the subfloor installation concurrently because we need a way to walk through the first floor, plus a place to put all of our tools. I’ll be working on it in the evening this week as well as this coming weekend. I’m hopeful I can finish by Sunday, but we’ll see.

Steam Pipe Removal

I’m sorry folks. This post could have been full of exciting, spark-showering photos of angle grinding, but we didn’t take in-progress shots. In fact, I only took phone camera pictures, so on top of not being as interesting they’re also grainy and blurry. I’ll try to do better.

Steam pipes

Steam pipes

Anyway, here’s the old boiler and steam pipes in the foreground with the new boiler and new panel in the background. I finished taking down the steam pipes this weekend. I mostly used the angle grinder with a cutting disk, though in a few places I used the reciprocating saw with a metal blade and some cutting oil.

Water fountain

Water fountain

I was surprised to find that one section of the return pipes was still full of water, even though it hadn’t been running since last winter. I thought it would have evaporated by now, but I guess not. It eventually drained and I finished cutting it out.

Section removed

Section removed

Because some of the supports were literally falling out of the ceiling, I strung it up in places with wire and bungie cords while I was removing it. All of the pipe went into my scrap pile, which at this point takes up a decent chunk of the basement. Once the snow melts I’ll haul it over to the recycling yard.

Scrap pile

Scrap pile

Once everything was taken down it really opened up the basement. I also removed a leftover section of the old gas pipe while I was at it, just so I could call it 100% done. With the pipes removed and the chimney down, there’s nothing in the way of finishing the new subfloor, except for all of the stuff on the first floor I have to move out of the way. I’ve got most of the back section done, and I’m hoping the rest of it will go more quickly.

Pipes removed

Pipes removed

The old boiler will wind up going to scrap too. It’s not as heavy as I expected. It’s pretty amazing how much different this section of the basement is from when we bought the place. I suppose that’s true of the first floor, too, since it’s all gutted, but somehow this feels more substantive.

Frozen Over

We got heat in the nick of time, since it got really cold in early January in much of the country. In Chicago, the low of -16° on January 6th beat records. The second floor stayed nice and cozy, thanks to our new boiler and radiators as well as the attic insulation. The rest of the house didn’t fair as well, and we had frozen pipes in the basement, a frozen washing machine, and frozen condensate line and intake on our hot water heater. Fortunately our hot water heater is fancy enough to detect the problem and shut down, as well as display the problem on the screen, making that part easy enough to fix.

Heater in the basement

Heater in the basement

The frozen pipes, on the other hand, required a bit more work. I never put pipe insulation on because we haven’t had our rough plumbing inspection yet, since I’m waiting until we complete rough plumbing on the first floor. That decision proved short sighted. We had relocated our electric heaters to the first floor and basement in an attempt to keep things above freezing, but it’s so drafty there wasn’t much hope. We wound up thawing things out with a heat gun to get the water flowing, and fortunately didn’t have any pipes burst. I don’t know if that’s because the water filter is able to absorb the increase in pressure or just dumb luck. In any case I added not only pipe insulation but pipe heating cable, which wraps around the pipes and uses about 60 watts, compared to the ineffective electric radiators that use about 1,500 watts each. It has a built in thermostat to kick on only when the temperature is below 38°.

Pipe heating cable

Pipe heating cable

However, before we were able to get the insulation installed everywhere, and because they were sold out of the longer lengths of heating cable, not everything was wrapped, so we wound up having a second pipe freeze despite our efforts. The washing machine was another casualty. Since we neglected to turn off the water and drain the hoses, the water inlet valve froze and split apart. When we got back from our vacation I took the thing apart, found the problem, and we bought a new one and and got it installed. We’ve been catching up on laundry the last couple of days and disconnecting the hoses at night when the forecast calls for sub-zero temperatures. We also put a thermometer in the basement to keep track of the how cold it is down there. The good news is it’s staying above freezing in the basement when it’s 5° outside. I’ll try and determine what the danger point is, though there’s obviously a time factor in addition to outside temperature.

Thermometer

Thermometer

Meanwhile we haven’t made much progress on other projects. Between the freezing, a nice vacation to Cancun, and being sick after we got back, January hasn’t been nearly as productive as I had hoped. Instead of working on subfloor I’ve been taking out the old steam pipes, since I need to get them out before I can finish the subfloor anyway. I may do a post about it, but I haven’t taken any pictures yet.

Heat!

Oh, finally, finally we have real heat! Up to this point we’ve been relying on a collection of electric heaters meant to supplement rather than stand in and even running four of them and consuming 6,000 watts of electricity in the process, it’s been cold. The insulation helped quite a bit, but ultimately we just needed the radiators working.

Mechanical Panel

Mechanical Panel

Lester finished up the other jobs he’d been working on and started working more seriously on our project. Over the course of a couple weeks he got the mechanical panel built out and the boiler hooked up. We figured out where we were temporarily putting the radiators on the second floor (until we remodel the floor and install in-floor radiant) and Mike helped me mount plywood panels to the wall so we could mount them. We also got the old steam radiators out onto the back porch.

Plywood panels

Plywood panels

I had originally wanted to run the PEX tubing that supplies the radiators through the attic, so Lester was going to put a manifold on the second floor. I decided the manifold could go behind the dishwasher since it’s on the wet wall and that spot will be in the master bath once we remodel. Unfortunately, when I pulled out the dishwasher and cut open the wall I found that spot occupied by five different supply and drain pipes.

All of the pipes

All of the pipes

Instead Lester put the manifold on the first floor and ran the PEX through the first floor. That may complicate things later, such as the plumbing that needs to go right where the manifold is and the ceiling where the tubing is running, but I guess we’ll figure that out when we get there. Top priority was getting heat.

Radiator being warm

Radiator being warm

With the radiators mounted and everything connected, Lester fired up the system and soon it started to get warm. We’ll still use one or two electric heaters if it gets too cold outside since the radiators are sized for our future insulation rather than the current lack thereof, but the difference in warmth and comfort is profound.

We had one hiccup though. After we got back from a long weekend with my family we discovered that the pipes had frozen. I had put an electric heater on the first floor but the circuit tripped so it wasn’t running. Fortunately there was no damage and we got everything thawed back out. This weekend I’m planning to get some pipe heating cable since its much cheaper to run than a 1,500 watt oil-filled electric heater.

Estimating

State of things

State of things

I talked a while back about the need to get the subfloor in, and how we wanted to hire it out. So far that hasn’t happened. We put out a few requests for quote, one came back quite high, one never got back to us, and one said that we didn’t actually need to level the floor. Since I don’t want a ¾” slope in the floor, I started work on the back section myself with the help of Mike, Sarah’s dad. It’s been slow going, though we haven’t exactly been working on it constantly. We made a little progress last weekend but got sidetracked insulating the attic, which incidentally has been a marked improvement.

I’m trying to work out how long it’s going to take to do, but there are a lot of variables involved. For example, Sarah’s in the midst of writing final papers and we’re heading into the holidays, so I don’t have a ton of optimism about making much progress the rest of the year. We’re taking a much needed vacation in early January, but I’m hoping to switch into high gear after that. With Sarah done with grad school I should be able to devote a lot more time in the evenings to working on the house. I also expect that once I figure out the best process for leveling the floor and get the hang of it, it should go faster than it has thus far.

The sooner we get the subfloor done, the sooner we can get heat in the first floor (assuming Lester ever finishes the boiler install). It’s also the sooner we can frame, spray foam, and start really making progress. If I can finish the subfloor by the end of January, I really think there’s a chance we could move into the first floor by the end of the year (2014). I may be delusional, but so long as we hire out the electrical and plumbing and don’t run into too many surprises, it seems like it’s possible.