Tag: concrete

Basement Retaining Wall and Footing Curb

We’re still waiting on our plumbers to do the re-lining of the sewer and the new water supply line. They in turn are waiting on approval from the City, which is being difficult. Apparently the connection between our sewer line and the sewer main under the street is damaged, and City is determining whether we need to repair it to do the re-lining.

Interior footing curb forming

Interior footing curb forming

In the mean time Mario, our concrete guy, is going like gangbusters to move things along. We can’t pour the basement floor until the plumbers finish their work, but we can work on the back stairs. After I removed the back steps down from the first floor, he re-dug out the hole we had filled behind the house and knocked out the existing retaining walls. For a rare change, rapid progress was being made without me being directly involved.

Nighttime concrete

Nighttime concrete

Within a couple days, Mario got the forms in for the new retaining wall as well as for a curb around the inside perimeter of the basement, since the existing stone block footings were exposed from the digout. Then, unexpectedly, Tuesday afternoon the concrete truck arrived a day ahead of schedule and Mario and his assistant wound up working until 10pm to get everything poured, smoothed, and cleaned up. Anything ahead of schedule is rare indeed with our project!

Retaining wall, formed, braced, and poured

Retaining wall, formed, braced, and poured

The forms came off the retaining wall yesterday and soon the stairs can be formed. I need to get the drain for the landing outside the back door roughed in and then Mario can get that and the stairs poured.

Completed retaining wall

Completed retaining wall

The forms are still on the footing curb, but you can definitely get a feel for the difference it makes in the basement. It’s really starting to feel like we can get a floor poured and start putting up walls, if the city would just sign off and let the plumbers get to it.

Back Steps Demo

Back steps

Back steps

This project was a quick one, but it portends bigger progress afoot. When we took down our back porch we left the stairs from the first floor down to the ground and the steps from there down to the basement. In fact, I shored up the structure underneath it, Matt B and Dean built a railing for it, and Sarah and Matt B cut a new piece of plywood for the floor of it, all so we could have usable back steps and a way to get from inside the house to the back yard. After I took out the concrete steps that led into the basement to make the ramp, the wooden porch steps to the side remained as a safer way to get in and out of the basement. Well, this past weekend I demolished the back steps.

Demo in progress

Demo in progress

This is in preparation for the new concrete retaining wall and steps that will lead from ground level down to the basement. We’re replacing the existing retaining wall and steps because we want to put a deck on the back of the house, which means the stairs need to go to the left instead of straight or right as they do now.  It actually makes more sense to go to the left anyway, since that’s the side of the house that has the sidewalk to the front.

Steps removed

Steps removed

Once the new wall and stairs are in place, we’ll build some temporary stairs down from the sliding door, since we won’t have the deck for some time. In the mean time we’re going around to the front or climbing in and out, sometimes with the help of a step-ladder. Hopefully the concrete guy will be starting in the next few days and we can get the temporary stairs built in the next few weeks. The plumbers finally started yesterday and I met with some tuck pointers that should be able to fix up the basement door and window openings in a couple of weeks, and last night we picked up the new exterior door for the basement, so we’re making progress on a few fronts.

Basement Floor Removal – Part 2

Clearing out debris

Rob clearing out debris

We kept up work on the basement floor, but the more I used the concrete saw, the more I used the sledgehammer and rotary hammer. The saw was simply too slow and produced too much dust, even using water. I worked out a technique with the sledge where I could get a single crack running the length of the concrete, maybe a foot from the edge, then use the rotary hammer to split off chunks. It wasn’t perfect, but it made shorter work of the floor than the saw.

Quality floor

Quality floor

The concerns I had with using the sledge, namely the ceramic tiles and the clay sewer line, were misplaced. With some safety goggles and a few thwacks, the sledge makes quick work of the tile. The sewer line is buried deep enough that I’m not worried about cracking it, especially since a fair portion of the floor wound up being suspended a few inches over the dirt, leaving cavities beneath it (including an old rat nest and a whole section of bricks).

Breaking up the floor

Collin breaking up the floor

We got the dumpster delivered last Thursday morning, and Sunday Sarah’s parents, sister and brother-in-law, as well as her nephew Collin and two of his friends came out to help load all of the concrete into the dumpster. It was a long day and at one point we started getting concerned it wasn’t all going to fit in the dumpster, but ultimately we got everything we had broken up loaded. There’s just a section at the front left to finish that we’ve been working on this week and hope to wrap up this weekend.

Back of basement

Back of basement (also bricks from under the concrete floor)

We left a small section of floor at the back of the basement that has the washer, dryer, chest freezer, and hot water heater for the time being. We’ll have to remove that later, when we temporarily move out and the sewer and water main are replaced. In the mean time we’ll start excavating the plumbing and get some quotes on that work, and I can finish the masonry and lintels around the front bay windows and start installing the new windows.

A big thanks to Mike, Lee, Nicole, Rob, Collin, Dylan, and Dustin for all their help!

Basement Floor Removal – Part 1

LED lights

LED lights

We’ve been hard at work in the basement. Since getting the new electrical installed and putting in the LED bulbs, we’ve pulled up all of the linoleum tile to make way for concrete floor removal. I bought an electric concrete saw from Amazon, but it uses a 20-amp plug. As it happens, we now have two 20-amp outlets, thanks to the new electrical, but we don’t have a 20-amp extension cord. Home Depot didn’t even carry one, aside from a 9-foot “appliance cord” that wasn’t going to reach very far in the basement. I ordered the extension cord from Amazon as well, but I didn’t want to sit idle over the weekend. That meant it was time to break out the sledge hammer and do things the old fashioned way.

 

Using a combination of sledge, pry bar, and my rotary hammer in chisel mode, Sarah and I managed to break up all the concrete on the North side of the basement. We spent a fair number of hours on it Saturday, Sunday, and last night. The other half of the basement (technically sixty percent) we’ll use the saw, since it’s covered in ceramic tile and we don’t want to crack the sewer pipes running somewhere underneath it by swinging the sledgehammer too much. My hands are pretty sore from the sledging we did so far, so switching to the saw sounds like a big improvement. The problem with the saw is dust. For that I’m hoping the shop vac attachment will make a difference, since we can’t use water with the electric saw.

Sarah ordered a dumpster for Thursday, and we’ll have it for two weeks. We need to have the whole thing broken up and hauled out by then, aside from the back corner where the water heater and laundry are. Those can wait a little while longer.

Beam Project: Footings

Settle in kids, because this is a long post. First off, I finished leveling the back beam, despite one of the hydraulic jacks slowly losing pressure. I picked up another jack post since the back beam sagged in the middle and I wanted to prop it up with the jack. I also removed the last of the stud wall under the beam, meaning it was now completely supported by the jack posts and hydraulic jacks. That in itself felt like an accomplishment. Then I finished building the temporary support wall, making it officially a pain in the ass to do laundry.

Temporary wall

Temporary wall

With these preparations complete, last weekend Eriq came down and together we cut the concrete floor using a circular saw with a masonry blade. The plan was to get the two holes completely dug out in preparation for pouring the new concrete footings. Unfortunately once we had the concrete floor out we found old stone footings under the floor in both locations.

Original footing

Original footing

Removing these footings proved challenging and we wound up spending the rest of the afternoon prying them out of the holes. The task was made more difficult because all of the ground under the house seems to be solid clay. Fortunately that means the holes stayed nice and straight and didn’t cave in, but digging in it was especially challenging. Initially we were trying to break up the old footings, but stone proved harder than concrete and we ran to Home Depot to get a longer bit for the rotary hammer, hoping to drill holes through it and then break it into chunks. Once we drilled the holes we noticed the whole thing was moving and realized we could pull it out in one piece.

Stone footing

Stone footing

The second one we didn’t bother drilling holes in and just pulled it out. The stone footings were limestone but one of them had a sandstone cap on it, perhaps to help manage drainage. The strange thing is that the floor was poured over these, so whatever columns had originally sat on these were long gone. I planned to dig the rest of the holes during the week, but I ran out of time since I also had to pick up concrete.

The footings specs are 30″x30″x18″, and since there are two, that wound up being thirty-two 80lb bags of 5000 psi concrete, plus I bought a couple extra just in case. Combining the limits of the trunk of the car with the $5 off $50 purchase coupons we had meant we had to break it into several trips. All told we spent around $150 on concrete. I spent Friday evening and Saturday morning digging the footings out, though when my friend Mike showed up with the concrete mixer he said they weren’t wide enough at the bottom. I had failed to employ measuring tape technology to confirm the holes didn’t taper as they went down, so it took us a couple more hours to get the holes right.

Measured holes

Measured holes

Next Mike made up the rebar. Because he does road construction he skipped the regular method of just floating in rebar as you go and built rebar cages to go into the footings, set on concrete blocks to keep them a couple of inches off the bottom. Assembling these went pretty quickly, but it was after we placed them and remeasured that he decided we needed to make the holes deeper so there would be enough concrete over the top of the rebar.

Rebar cage

Rebar cage

That meant we had to take them back out and spend more time digging out the holes, adding to the already massive pile of clay in the back yard that we took out in five gallon buckets. We’ll need to figure out where and how to get rid of that. My initial plan of just spreading it around in the yard was hatched before I realized it was all clay and not soil.

Footing depth

Footing depth

We verified our depth and placed nails at the edge to keep track of how high the concrete needed to be and to make sure it was level. I determined the depth to dig by starting with the outside wall footings. The bottom of the outside wall footing is the maximum we can eventually dig down the floor without underpinning. Then we’ll add a layer of stone and rigid foam to insulate the floor, which will have radiant heating. The bottom of the floor is the top of the column footing, so from there we measured down 18 inches. The laser level has proved invaluable for nearly every step of the process. I think even if I only bought it for this one project it would have been worth it, but I know it will be handy when we do the subfloor, the cabinets… everything really. I put it in the corner and from there had a level line that reached the corner outside wall footing we had dug out as well as the two column footings we were currently digging, making it easy to keep track of our depth given the fact the floor isn’t level at all.

Filling with concrete

Filling with concrete

We discovered the garden hose in the garage was full of ice and we couldn’t use it without waiting for it to thaw so we ran to Home Depot and picked up another one. Then we found the outside spigot was frozen and had to hook up to the faucet on the first floor. Finally we were able to start the concrete operation. Mike mixed up the bags in the portable mixer while I brought bags from the garage and took buckets into the basement. He added portland cement to the mix in order to get a better consistency, about three cups per bag. As we were finishing the first footing it was looking like we might be shy on concrete but in the end we had two bags left over, exactly the overage I had calculated.

Finished footing

Finished footing

Mike used his concrete vibrator to remove any air pockets and even out the consistency and then troweled off the surface to make it smooth. It certainly doesn’t need to be perfect since these will be covered when we put in the floor, but they look nice just the same. This picture also gives you an idea of how much ceiling height we’ll be gaining. The new floor will be four inches thick on top of the footing, so it’ll be about six inches lower than it is now. That doesn’t sound like a lot, but it’s the difference between having to duck under the beam for me at 6’2″ and being able to stand up straight for Sarah’s brother who’s 6’8″.

Plastic cover

Plastic cover

We put some plastic on top of the concrete to help it cure more slowly. It needs seven days to cure, but it will be longer than that before we put the new columns on them. Swapping the wooden beam for the new steel beam and installing the columns is probably about a month out since we need to coordinate a lot of people to come and assist.

Dirt pile

Dirt pile

Once we had finished I spent the whole evening yesterday just sitting on the couch. I’m really sore after digging the holes, carrying out the dirt, and then carrying in all the concrete, and I’m sure Mike is too, but we’ve reached a milestone we’ve been working toward for a while. It feels really good to have something to show for all the work and finally have a piece (okay, two pieces) of the new house in place. The only other thing in the entire house that is the “end product” is the electric service, and we didn’t do that ourselves, so this is kind of a first for us. We’d both like to extend a big thanks to both Eriq and Mike for all their help with the footings.