Tag: conduit

Electrical Cleanse

Original panels

We finally have no old electrical in our house! When we bought the house, there were two panels for separate electrical service between the two floors. The whole thing was spliced and festooned with a mixture of wiring from various electrical epochs, like the strata of some ancient city. Much of the house was run with cloth-wrapped cable inside the flexible, coiled “BX” metal conduit. Our house inspector, and later our insurance inspector called it out as a risk. We knew from the start that we’d have to replace it all, but it’s been a long, gradual process. This process started with the basement demo, where I removed all manner of fire hazards. It continued with the first floor demo, then went back to the basement when we started our structural work, and jumped ahead with our new electrical service. It didn’t make a lot of progress for quite a while, but finally early last year we put in new electrical in the basement, got rid of more of the old stuff when we did the back porch demo, and most recently when we started on the second floor.

New panel and old panel

I disconnected the second floor electrical before we did demo, pulled out the majority of the BX cabling during demo, and finished shortly afterward, but there was still more to do. There were three BX cables and one conduit running up to the second floor, including two that ran up the back of the house (on the outside), requiring me to use the extension ladder to get them down. I had also left one BX cable with one outlet in place to service the first floor, but since that was fed off the old electrical panel box, it had to go too. There are now three separate extension cords running into the first floor from separate circuits, servicing the freezer, washer and dryer, as well as lighting/surge strip outlets.

New panel alone

This past weekend I got everything removed but the old electrical panel itself, which included several random junction boxes mounted around the panel and short lengths of BX cable connecting them all. The old electrical panel was itself only functioning as a junction box, since Percy had moved all the breakers to the new panel when he put it in, but that meant I still needed to pull out all the breakers from the circuits I’d removed. Saturday morning I shut off the power on the main breaker and moved quickly to get the remaining wires disconnected, the old breakers out, the remaining breakers consolidated at the top of the panel, and the old panel finally pulled off. The old electrical is finally, officially, gone! I printed some nice new labels to replace the masking tape and sharpie that had served to date. I still need to put some blanks in to cover up the removed breakers (there’s always got to be some little remaining task), and I want to remove the boards that the old panel was mounted on, but I’m still happy that, at least with the electrical, everything we have is new. I’ll be able to say the same about the plumbing just as soon as we get the rest of the old stack replaced.

New Basement Electrical

Before we start ripping up the floor of the basement, it made sense to put in the new electric. For one, it’s easier to put in overhead lights with the floor a little higher, but more importantly we want to cut down on work that needs to be done after the floor is done since we’ll be in a hurry to get moved back in. Plus, having good lighting down there instead of some crappy dangling fixtures will make working on the floor a little better. I debated doing the electrical myself, but in the end I just called Percy, our electrician, and he and his assistant Kevin got it done in a few days, where it probably would have taken me a month. Percy will come back after the interior walls are up to add a few more outlets and switches, but this gets us 90% of the way there.

New switches and outlets

New switches and outlets

We went the typical recessed can light route. The ceiling in the basement won’t be very high, so anything that sticks down is less than ideal. I bought a few LED light bulbs to decide what color temperature and style we like before ordering a whole set of them. We settled on the 3000K “bright white” since they’re a nice compromise between the 2700K yellowish “warm white” and the 4000K laboratory “daylight”. The bulbs came out to $12 each, cheap for LEDs, but expensive relative to CFL and incandescent until you consider the operating cost and lifetime. A regular 65W bulb costs $3 and  lasts 1,000 hours. A CFL costs $8, uses 14 watts, and lasts 8,000, while an LED uses only 8 watts and lasts 25,000 hours. Including replacement costs and electricity, every thousand hours of incandescent use costs about $13.85, compared to a CFL that costs $3.38 and an LED that costs $1.82. Since we’ve got nineteen lights just in the basement, the payback is there even vs CFLs. We spent $75 more on LEDs than CFLs up front, but even ignoring that the LEDs last three times longer, the electricity savings will pay that back before the CFLs are half used.

New can lights

New can lights

I was concerned about mounting the switch and outlet boxes on the brick, since even though the metal is galvanized, moisture can corrode it. The old finished basement had some extremely rotted boxes and conduit that we don’t want to recreate. Percy sprayed the backs of all of the boxes before putting them up with a rubberized coating to prevent water contact from the walls. Our hope is that along with improved water management, the electrical will stay dry and last a long time.

Outlet box spray coating

Outlet box spray coating

The plan is to install a foam panel system on the exterior walls that will provide a drainage plane behind the insulation. These systems have raceways for the electrical so we can just fit them over the installed conduit when we finish the basement. That will ensure any water that comes through the brick will be able to drain away and that the wall itself is impervious to water and won’t rot. It’s exciting to see more progress,and to see how much the basement has changed so quickly, especially since I didn’t have to do all the work!

Mechanical Room Preparation

With the hot water heater question sorted, I need to get the area of the basement that the water heater and boiler are going into ready. Eventually this will be the mechanical room… when we frame out the basement, after we lower the basement floor, after we finish the rest of the house. We already ran gas line, but there are still a few things to be done.

Mechanical room wall

Mechanical room wall

The boiler will be hung on the wall, and since the basement isn’t framed out that means it’s going on an outside wall. We don’t want to mount it directly on the brick because we want our house insulated and air sealed. That means we need to frame the outside wall where the boiler and panel will go. However, because we’re going to eventually lower the basement floor, we can’t just put a sill plate of the wall on the floor, we need to attach the studs to the brick wall. To ensure air and moisture management, we’ll use sill gasket behind the studs and fill the holes with caulk. The area between the studs we’ll fill with closed-cell spray foam.

Before any of that can happen, I need to prepare the wall. As is typical of our house, years ago someone saw a problem and went out about fixing it the wrong way. In this case, moisture problems with the brick foundation wall were not corrected by fixing gutters, redirecting storm water, or repointing the brick, they were “fixed” by slathering (parging) mortar or cement all over the brick wall on both sides in an effort to water seal it. This is generally a terrible idea because it traps water in the brick, rotting it from within. The ineffectiveness of this strategy is revealed by the coat of paint they put over the finished product which is now bubbled up and crumbling off.

So I’ve been removing the parging with my rotary hammer in chisel mode and a pry bar. It doesn’t need to be perfect, but the wall does need to be plumb. While the brick itself is pretty straight, the parging is thick enough in places to make for a wonky wall. Removing it is tricky because the parging doesn’t want to come off and it’s easy to damage the brick itself.

I also need to run electrical from the panel to the mechanical room. Chicago code requires EMT conduit, and in this case it’ll be ¾” because I need to run several circuits (lighting, hot water heater, boiler and pump, smoke detector, and eventually the air handler and HRV). I’m hoping to get both the wall prep and the electrical done by this Monday. With that out of the way we can get the hot water heater installed and focus on the remaining tasks for the boiler prep.