Tag: demo

Second Floor Demo Prep

With the drainage project finally wrapped up, we’re getting ready to demo the second floor! As in the past, we’re having a demo party where friends come over to smash the hell out of the walls and tear everything down. To make sure this process goes smoothly, safely, and makes as little mess as possible, we have some work to do up front. First, we need to clean up the first floor. With us living in the basement, and the second floor empty, we’re using the first floor as storage. Between all of our projects, moving to the basement, and life in general, it has a tendency to get away from us and turn into a cluttered, disorganized mess. When we demo the floor above, dust and debris are going to rain down between the floorboards, so everything needs to be as contained and protected as we can make it.

Empty kitchen

Empty kitchen awaiting destruction

I tackled the back (everything behind the wet wall) since this is my de facto workshop where all the tools are kept. After we rushed to finish the basement, I wound up bringing them back up in boxes and not putting them away. I re-organized and cleared out the worst of it, but honestly, I still have a lot more cleanup to do. However, the critical part was I made a space big enough to put all of the kitchen cabinets from upstairs. When we bought the house, we got a bunch of free kitchen cabinets from Sarah’s grandmother (who in turn had gotten them from a friend of Sarah’s parents when they remodeled their kitchen). We’re done with them now, so we’re giving them to Sarah’s parents, since they’ve bought rental property in Florida and want to redo a kitchen down there. Until they pick them up, we needed them off the walls and in the first floor. Sarah cleared up the front of the first floor, which was a bigger process since it involved not just organizing, but throwing away what we don’t want, donating what we don’t use, moving some of what we want into the basement (and finding homes for it all down there), organizing the rest of it into bins and boxes, and finally, covering it all with tarps and drop cloths.

I disconnected the water, which was complicated by the fact we still have the washer and dryer on the first floor and by the way the plumbers replaced a perfectly good dielectric union with a brass female adapter and my side-drain valve with a regular valve (both for no apparent reason other than to piss me off). That meant to disconnect the hot water I had to cut the copper pipe past the valve (which was full of water) and drain it that way. I still need to solder a cap on the pipe. For the cold water (which is all we have for the washer) I was able to reconfigure my press-fit PEX fittings (so easy!). I also disconnected the gas line that went to the stove upstairs. That was made more difficult by the fact it was one 12′ pipe going from the basement to the second floor. Disconnecting it was easy, getting it out of the wet wall was a bit more difficult. We had Lester, our radiant contractor, disconnect and drain the radiators a couple of months ago, so I was able to just lift those off the wall and move them downstairs. I unscrewed the thermostatic valves and fancy stainless steel fittings and saved them in a bag. These radiators will eventually be in the attic bedrooms, since the other stories will have radiant floor heating.

I turned off the electrical circuits for the second floor and took down the ceiling fans and light fixtures, but I still need to remove the actual BX wire cables strewn through the attic. I reclaimed the outlets (few that there were), which we’d installed new when we bought the house. The whole upstairs only had one light switch (in the bathroom) since everything else was on pull chains and a couple of fan remotes. Honestly, one of the nicest parts of the basement is the normal complement of outlets and switches, since they were in short supply upstairs.

Debris chute

Debris chute

Sarah ordered a big dumpster and it was dropped off in the back yard on Friday. Monday I built a chute out of the extension ladder and some 2x4s and plywood to go from the back door of the second floor down to the dumpster that will make the demo process go much faster. We discovered when we demoed the first floor that balloon frame houses lend themselves to a particular order of deconstruction if you want to contain all the plaster dust and mess. By demoing the ceiling first, all the debris falls into the still-enclosed rooms rather than into the wall cavities and into the floor below. By saving the flooring for last, we prevent (some of) the mess raining down between the subfloor boards. Also, by demoing the ceiling before the demo party, we prevent some of the more dangerous aspects of wanton destruction with large groups of people.

Chute close-up

Chute close-up

I got underway with ceiling demo, starting in the back bedroom and kitchen and working forward. We insulated the attic with blown-in cellulose a few years ago, so there was a lot of fluff shoveling, but the chute is working as hoped. The top of the chute is slightly higher than I’d planned, so I need to lower it a bit, but otherwise it’s a vast time saver over hauling everything down by hand. When we prepped for demo of the first floor we took down all the trim, but in the second floor, at least for the windows, I’m concerned the trim is actually holding the windows in place. They’re all cheap replacement windows and they’re less than professionally installed. We may take it easy on those until we’re ready to replace them. The weather is getting cooler and we don’t want any gaping holes in the exterior walls, let alone the possibility of broken glass and injured people.

I expect to finish ceiling demo tonight, the kids will be out of the house with grandparents for the whole weekend to avoid any noxious dust contamination, and we’ll get this, quite literally, knocked out!

Back Steps Demo

Back steps

Back steps

This project was a quick one, but it portends bigger progress afoot. When we took down our back porch we left the stairs from the first floor down to the ground and the steps from there down to the basement. In fact, I shored up the structure underneath it, Matt B and Dean built a railing for it, and Sarah and Matt B cut a new piece of plywood for the floor of it, all so we could have usable back steps and a way to get from inside the house to the back yard. After I took out the concrete steps that led into the basement to make the ramp, the wooden porch steps to the side remained as a safer way to get in and out of the basement. Well, this past weekend I demolished the back steps.

Demo in progress

Demo in progress

This is in preparation for the new concrete retaining wall and steps that will lead from ground level down to the basement. We’re replacing the existing retaining wall and steps because we want to put a deck on the back of the house, which means the stairs need to go to the left instead of straight or right as they do now.  It actually makes more sense to go to the left anyway, since that’s the side of the house that has the sidewalk to the front.

Steps removed

Steps removed

Once the new wall and stairs are in place, we’ll build some temporary stairs down from the sliding door, since we won’t have the deck for some time. In the mean time we’re going around to the front or climbing in and out, sometimes with the help of a step-ladder. Hopefully the concrete guy will be starting in the next few days and we can get the temporary stairs built in the next few weeks. The plumbers finally started yesterday and I met with some tuck pointers that should be able to fix up the basement door and window openings in a couple of weeks, and last night we picked up the new exterior door for the basement, so we’re making progress on a few fronts.

Garage Demo

The garage

The garage (doors removed)

Our whirlwind of demo continues with the destruction of our terrible, terrible garage. The garage is a tragic story, really. A perfectly good, new, professionally built garage was put up a few years before we bought the house. Apparently it wasn’t big enough, though, so the previous owners poured a two foot concrete pad extension on one side, cut one wall off, and moved it over. Then they just added boards to bridge the gap and shingled over it. The main door was replaced with a larger one and at the back (yard side) they put a smaller door, which may or may not have been the original front garage door. In any case, the structure was badly compromised, and by the time we bought it, water, rats, roaches, and plants were getting inside. We’ve used it as-is for the last few years, with big plans for a flat-roofed masonry garage and a yard-side fireplace waiting in the wings.

Roof removal

Roof removal

With our basement dig out pending and a giant pile of debris from the porch in the back yard, we needed to tear down the garage to make way for dumpsters. Sarah’s parents came down to lend a hand on Saturday. There was some doubt as to how long the process was going to take, but we had the whole thing down by mid afternoon.

We wanted to get the yard closed off before calling it a day. We started work on the gate, but we only got one side up before it started getting late. By then dinner had arrived, so we propped up the other fence panels and called it a day. Sunday I broke down the garage pieces, we got the pad swept up, and I put together the rest of the fence and gate across the back.

Fence installation

Fence installation (also Derek)

The gate doesn’t work all that well at the moment. Because the new fence on the right doesn’t have very good footings and because I put in the posts with spikes instead of footings, the gate needs some center support to stay rigid. That in turn make it difficult to open and close. I may put a wheel on at least the left panel to make it easier to get the car in and out. When you open the right side gate, the fence leans enough that the neighbors side gate opens by itself. In any case, the garage is down and the first dumpster is on order for Friday, so now we need to get a path cleared in the yard!

Back Porch Demo

We want to dig out the basement, and the only door is at the back. To be able to get a dumpster into the back yard and haul loads of dirt straight out, we need to tear down the back porch and the garage. We’re planning to replace both anyway, so doing it now makes sense. The back porch is a fully enclosed, two-story, vinyl-siding-clad beast. We took out the stairs from the first floor to the second a while back so we could put in the back sliding door, so it just has steps down to the back door and to the basement.

The first step was to move all of our accumulated stuff off the porch, including the old radiators. Fortunately I found a used radiator company to come and take them and even pay me a bit for the trouble. I disconnected and removed all the old electrical and moved the phone line box from the outside of the porch to the outside of the house.

Windows and doors removed

Windows and doors removed

Saturday morning I started work removing the doors and windows and was soon joined most of by Sarah’s family. We discovered that because the porch was enclosed after it was built, the walls weren’t integral to the structure. The walls consisted of some horizontal 2x4s attached to vertical beadboard, some of which was twenty feet long, and vinyl siding on top of that. While not very strong it held together remarkably well. The big challenge was the right side, where there was no landing or stairs to work from, just a big open space.

Walls coming down

Walls coming down (with Mike and Matt L)

We managed to rip down the right side of the wall in one giant piece. You can see from this photo how the floor only extends to the door in the middle of the house. With that piece down, the rest of the back wall was pretty straightforward.  The right side wall was a bit interesting. We wound up pulling the pieces of beadboard off individually and then the vinyl siding, which at that point was just hanging from itself.

Walls removed

Walls removed (with David and Matt L)

By that point is was evening and we wrapped up for the day. The next day we had a bunch of friends over to start working on the structure. The roof was an open question, since there wasn’t a great way to reach most of it. In hindsight, it may have been better to tear the porch down back when we took out the stairs, since having the landing would have made this process easier, plus we wouldn’t have had to worry about breaking the new sliding door with a piece of falling debris.

Roof removal

Roof removal

We used the ladders and a piece of fencing we bought to fill in the gap to shield the sliding door from the chunks of falling roof. We used a rope on the right column to pull it down after cutting it near the base with a chain saw. At first we tried the pictured system of pulleys to pull it down, but the angle was wrong so we wound up not using them. Unfortunately the porch beams were pocketed into the sheathing, so I have to go back and patch the holes in the outside wall before birds start nesting in the walls. I ordered an extension ladder as well, something that probably would have come in handy for this project, since the folding Werner ladders aren’t quite long enough.

Roof removed

Removing the last section of roof (with Dean, Matt B, and Drew)

We had a bit of a scare pulling down the last section of roof because the left column started to lean out, not only getting close to our power line, but pulling away from the beam that held up the second floor of the porch! After we got the roof section off things went quickly and we got the second floor structure removed. I also screwed the second floor door shut so we won’t have any accidents.

Finishing up

Finishing up (Dean and Matt B)

The first floor went pretty quickly too. We left the section by the stairs so we can still get in and out. We moved all of the drywall out of the garage and the freezer out of the basement and into the first floor, and then Dean and Matt built a new railing while I put up some house wrap over the sheathing and patched the lower two holes in the wall.

All done!

All done! (With Dean, Drew, and Hector)

We now have a massive pile of debris in the back yard (scroll back through the pictures to watch it grow). We’ll need to live with it until we get the garage torn down and a dumpster into the yard, but that should just be a few weeks. I plan to salvage some scrap material to build a ramp that we can use to get wheelbarrows of dirt into the dumpsters when we dig out the basement. This was a big two-day project and we couldn’t have done it without tons of help from family and friends.

A huge thanks go out to the Saturday crew: Mike, Lee, Matt L, Amy, Rob, Nicole, David, Collin, Dylan, and Dustin, as well as the Sunday crew: Dean, Hector, Drew, Anna, and Matt B. Thanks everyone!

Porch Stair Removal

When I originally started building instead of demoing, I was really looking forward to it. Building gives you a sense of progress that demo does not. After demoing you have a sense of accomplishment, but you can’t really say that things are “better” when you’re done. However, after months of construction, going back to destruction felt really good. While it’s really hard to build right, it’s hard to demo wrong.

So, what are we doing? The porch stairs are in the way of the new sliding door that we’re putting at the back of the house. I already moved the electrical, and I got the old radiators that had been sitting on the second floor porch down during the week, so taking out the stairs is the next task. They consist of two runs separated by a landing. The landing also needs to come out, and I need to make railings so that everything is safe for our son Derek.

Upper railing

Upper railing

The process went fairly quickly. I started with the upper railing, taking it off the stairs and re-purposing it to the second floor porch. Then with a bit of sledge hammering and prybarring, I took the treads and risers off, top to bottom. Then I pulled out the stringers, using my reciprocating saw to make short work of it. Next was the floor on the landing, followed by the railing, treads and risers on the lower stairs. Then I took down the structure of the landing and the stringer for the lower run. I left the stringer on the outside wall, since the porch isn’t built very well and I didn’t want to loosen anything (such as siding) by prying against the wall. I did cut the stringer back to make room for the lower railing. This one was a bit more involved, since it was an ‘L’ shape, it wasn’t braced on both sides, and the bottom didn’t rest on framing, so I had to add some reinforcement.

Lower railing

Lower railing

With that all done I started cleaning. I wound up filling two toters with the scraps. There wasn’t much that was worth saving, since it was coated in several coats of unknown paints. So far Derek and Emily have tested for low levels of lead and we want to keep it that way. I have a bit more scrap to cut down so that it will fit in the garbage, but otherwise it’s done. I started planning out the sliding door installation, so that’s the next undertaking. Back to construction!