Tag: foundation

Beam Project: Measurements

The first step is to get all of the precise measurements and check how far off of level we are. I bought a laser distance measure and a self-leveling cross line laser level. These were each about $100 each and in addition to being incredibly helpful for this project will be useful for many of the projects going forward.

Checking beam level

I started by checking the beam for level. I drew a mark under each floor joist along the laser line and then measured from the joist down. I then marked which joists were lower or higher than average. The variance was about a half inch in either direction. Then I turned the level the other direction to check the floor joists. I found that the floor joists sagged by about an inch from the outside wall to the beam. Determining level without the laser would have been painstaking and not as accurate. I have a six foot level, but using it to find the level of the whole basement would have sucked. Since you can’t trust the beam, the joists, or the floor to be level, all you can do is find variance. This will be especially important when I dig the footings so I know how deep to make them.

Checking joist level

I also measured the length of the beam. It is pocketed into the brick wall at either end, so I slid a piece of metal in to determine how deep the pocket is and added that to the total, which is roughly 44′. There will be two columns, so we’ll split the beam into three sections. The challenge in positioning the columns is that the floor above will also have open spans, so those columns need to be directly above the columns in the basement. The spans should be as short as possible, because their load bearing capacity drops exponentially with length. I referred to the floor plans, but a couple of the dimensions were off, so I had to adjust to get the exact locations of the columns. I determined the longest span will be 16′. Conveniently you can multiply 16′ x 24 lbs and get the weight: 384 lbs. This job will require some help.

Marking the footings

Finally I marked out the location of the footings on the floor. Unfortunately, there are studs and a 4×4 in the way, so I need to build the temporary wall so I can remove it. That means it’s time to get some jack posts and crank up the house.

Looking Ahead

We’ve been talking to the structural engineer, and while we haven’t figured out the exact plan we’re hoping to get the basement shored up. If we’re lucky we’ll find that the footings under the wall go a foot down below the basement floor. If that’s the case we’ll get the new steel header and steel support posts, as well as new concrete footings under the posts. Those new footings will be set deeper than the current floor, so that down the road we can dig out the basement floor and gain about 8″ of height. I was relieved to find out that we could do those two separately, because digging out the basement is expensive, and not something we really need right now. The support posts need to be done now, though, because the house needs to be leveled before we can remodel the first floor.

So far we’ve been working on the second floor and everything has been temporary stuff to make the house livable. The structural work is the first thing that’s actually fixing the house up, well aside from exterminating roaches. The exterminator told us we can move in, but I was disappointed to hear that we probably won’t completely eliminate them until we tear down the walls and then call the exterminators back to spray again. That means we’ll be sealing everything on the second floor up as tight as we can with caulk, wood fill, spray foam, and whatever else it takes. He said it was one of the worst infestations he’d seen.

Once we’re moved in and the condo is rented we’ll move forward on the structural repairs. Then we’ll work with an architect and plan out the rest of the project. In addition to the obvious stuff like new walls, drywall, and floors, we need to install new heating and cooling. We’d like to put in hydronic radiant heating and high velocity forced air cooling, but they aren’t cheap. High efficiency boiler, pumps and manifolds, condensers, blower and ductwork will run tens of thousands of dollars. We can do some of it in phases, but it’s probably the single most expensive part of the project. We’ve spoken with an HVAC guy and gotten some ideas, but it’s tempting to just go with traditional forced air, even if it means installing bulkheads.

We’ll figure it out once we get closer. Right now we’ve got more pressing needs, like getting the rest of the trim back up and the second floor painted, plus a laundry list of little tasks that add up to a lot of work.