Month: November 2012

Back in the Basement

20121118-155204.jpg

Sarah is almost done with her semester of school which means she’ll be on break for a bit and we can try and get some work done. We were trying to get an inch of spray foam in the first floor, but the more I look at it the less feasible that seems right now.

We have one of the many order of operations problems. We need a dumpster to clear out the rest of the piles on the first floor, but we don’t want to get it until we demo the foyer. We don’t want to demo the foyer until we get our permits, and who knows how long that will be.

The other thing we can work on, which should really be done before we get another dumpster, is finally replace the beam in the basement. I’ve been slowly working toward that goal for the last year, but I’ve been putting it off due to cost, time, and the non-trivial apprehension about the project.

So with a five week window and the holidays mixed in, I’m cleaning out the basement and putting together the plans, starting with digging new footings and building a temporary support wall.

Today I swept up the debris that’s been raining through the floor boards from the first floor, moved the lumber and scrap metal piles to the outside wall, and picked up the mess of tools and junk that had accumulated over the course of several other projects.

We ordered a laser level and a distance measurer. When they arrive in a few days we’ll do some measuring, get the steel beam and columns ordered, and start work on the footings.

Time is the Missing Ingredient

When we started this project we had an idea of how much work was involved and how much time it would take to do it. The plan was this would be a part time second job. We would work on the house in the evenings and hopefully keep our weekends mostly free. With this approach we’d spend 15-20 hours a week on the house, ideally both of us. With that kind of time commitment, we projected we could have the first floor refinished in about a year. Today, seventeen months later, the first floor is mostly demoed but a long way from finished.

Looking back, I still believe our time estimates were fairly reasonable, but they completely failed to account for a double whammy: having a baby and Sarah going to grad school. If it was one or the other, one of us could still work on the house while the other was occupied with school or the baby. Both means that while Sarah is writing papers and attending class, someone has to watch the baby. Both means there’s not much time to spend on the house.

While the time available to work on the house has plummeted and progress has ground to a near-standstill, we have gotten a few things done. I got the first floor bathroom window removed, the last of the hardwood floor is up, we’re sorting through the room full of lath, and we’ve filled the garbage toters with debris at least a few times. The problem is this progress has been over the course of the last several weeks. I wish I had a solution, but short of paying someone to do the work the only solution has been my mom coming once a week to watch the baby while I go downstairs and work for an hour or two and getting some work done on the weekends.

Things are slow on the permit side, too. We’re still waiting for Zoning to decide if we can have a front porch across the front of the house. We got them the new plat of survey with the neighbor’s building setbacks, more recently I sent them color photos of the front and back of our house and the neighbor’s (the two houses to the North and two to the South). Even though Green permits are supposed to be “expedited” they’re apparently backed up. The way things are shaping up, we won’t be done with the first floor for a very long time, and that’s just the first part of the project.