Month: December 2013

Estimating

State of things

State of things

I talked a while back about the need to get the subfloor in, and how we wanted to hire it out. So far that hasn’t happened. We put out a few requests for quote, one came back quite high, one never got back to us, and one said that we didn’t actually need to level the floor. Since I don’t want a ¾” slope in the floor, I started work on the back section myself with the help of Mike, Sarah’s dad. It’s been slow going, though we haven’t exactly been working on it constantly. We made a little progress last weekend but got sidetracked insulating the attic, which incidentally has been a marked improvement.

I’m trying to work out how long it’s going to take to do, but there are a lot of variables involved. For example, Sarah’s in the midst of writing final papers and we’re heading into the holidays, so I don’t have a ton of optimism about making much progress the rest of the year. We’re taking a much needed vacation in early January, but I’m hoping to switch into high gear after that. With Sarah done with grad school I should be able to devote a lot more time in the evenings to working on the house. I also expect that once I figure out the best process for leveling the floor and get the hang of it, it should go faster than it has thus far.

The sooner we get the subfloor done, the sooner we can get heat in the first floor (assuming Lester ever finishes the boiler install). It’s also the sooner we can frame, spray foam, and start really making progress. If I can finish the subfloor by the end of January, I really think there’s a chance we could move into the first floor by the end of the year (2014). I may be delusional, but so long as we hire out the electrical and plumbing and don’t run into too many surprises, it seems like it’s possible.

Unexpected Insulation

It’s a very cold December now, and we still don’t have heat. We’re subsisting on electric radiators, both oil-filled and baseboard. However, it dipped down to 10° over the weekend, and they just weren’t cutting it. When I got up Saturday morning, the thermostat in the living room said it was 53°. Sarah decided that we needed to insulate the attic. She said she would do it, but I’ve heard that song before and I know how it goes. With no insulation to speak of, the little heat we did have was going right out the roof. We don’t plan to remodel the second floor for another year or so, so even once we have real heat we’d still be losing a ton of it.

Not insulated

Not insulated

We debated buying the mineral wool batts we plan to eventually put between each floor, but they’re pretty pricey, and we weren’t sure how well taking them out and putting them back in later would work. Ultimately, we went with blown in cellulose because it was drastically cheaper, plus we had some Menards rebates from buying the subfloor that made it even more affordable. Including the machine rental we were out of pocket about $65, so it won’t take much heat savings to recoup. Sarah and I spent the rest of the morning pulling all of the random boards out of the attic (it’s been weeks since we had a scrap wood pile!). Her parents and nephew Aaron showed up in the early afternoon. There were some unexpected delays in getting everything, though, and we didn’t wind up getting the machine set up at the house until 7 pm. It was crunch time, but fortunately the machine was quick: we blew through 20 bags in 30 minutes. Each bag covers 40 square feet with 6″, rated at R-19.

Insulated

Insulated

We discovered that in our rush to take out the boards, we had knocked out the kitchen electric circuit, so I had a follow up job of fixing that. I wound up having to replace a length of BX cable over cloth-wrapped wires with one of our newer cable segments from the massive pile in the basement. Unfortunately that necessitated taking down the ceiling fan in the kitchen to get everything re-wired, but that’s all done now. The house is still cold, 64° as of this writing, but it’s not as bad as it was, and hopefully soon we’ll have real heat. The radiators were delivered earlier today, so now it’s all up to Lester (our radiant heating installer). He’s in the basement right now, hooking stuff up.

Chimney Removal, Part 2

All right, back to the chimney. In Part 1 I got up on the roof on a particularly stormy and unseasonably warm day (at least is started that way), took the top of the chimney off, and patched the roof. This was followed up later in the week with removing the portion of the chimney in the attic. A couple Saturdays ago we took out the second floor portion, which has the added wrinkle of us living there. To prevent dust and debris from coating all our stuff, we started by taping up some plastic sheeting.

With that in place I started work up in the attic, taking out a few feet of bricks before finally breaking through the plaster. At that point I switched to the second floor and a step ladder. Sarah spent most of the day on brick duty, where I lowered buckets of bricks down using our pulley system and she emptied them into the first floor, though she did try her hand at brick removal. I wound up doing most of it with a pry bar, forgoing the air hammer and the accompanying dust and noise.

We needed to get the whole thing done and patched in a day because it’s gotten cold outside and a giant hole into an uninsulated attic when you’re already relying on electric heaters because you don’t have heat is a really bad idea, mmkay? We finally broke through into the first floor around 7 pm. With that milestone reached it was on to framing and drywalling, which I think we wrapped up around 10. Sarah’s in charge of getting it mudded and painted. So far we’ve got the first coat on. I picked up the flexible paper corner bead and we like it better than the metal corners.

From there it was on to the first floor, where I took down another eight feet of bricks early last week while Sarah broke mortar off of bricks we’d already taken out. Will was over this past Saturday and finished it off, getting the top of the chimney down into the basement. Along the way we found that the best process was to knock the mortar off the bricks straight into the chimney. It’s bad enough hauling down buckets of bricks without having to also deal with the heavy, dusty, crumbly mortar. There’s an opening at the base of the chimney in the basement where we can just shovel the mortar out and take it into the back yard in a wheel barrow.

Chimney gone

Chimney gone

Our back yard has gotten even more attractive as of late. Now in addition to the giant mound of clay from the footings that’s been gradually melting (currently covered in leaves), the paint bucket planters, the garbage cans full of compost, and the scrap metal, we’ve added a tarp-covered stack of OSB, both a pile and a giant stack of bricks, and a pile of mortar. It’s quite the beautification program we’ve got going.

Beautiful back yard

Beautiful back yard

Oh well, that can wait for another day. We still have impressive piles of bricks and mortar in the first floor that need to be hauled out, along with the rest of the mudding, sanding, and painting to get the second floor looking respectable again. We’re planning to use some of the bricks to make the base of the columns under the front porch. The rest we’ll probably sell.