Year: 2015

Back Steps Demo

Back steps

Back steps

This project was a quick one, but it portends bigger progress afoot. When we took down our back porch we left the stairs from the first floor down to the ground and the steps from there down to the basement. In fact, I shored up the structure underneath it, Matt B and Dean built a railing for it, and Sarah and Matt B cut a new piece of plywood for the floor of it, all so we could have usable back steps and a way to get from inside the house to the back yard. After I took out the concrete steps that led into the basement to make the ramp, the wooden porch steps to the side remained as a safer way to get in and out of the basement. Well, this past weekend I demolished the back steps.

Demo in progress

Demo in progress

This is in preparation for the new concrete retaining wall and steps that will lead from ground level down to the basement. We’re replacing the existing retaining wall and steps because we want to put a deck on the back of the house, which means the stairs need to go to the left instead of straight or right as they do now.  It actually makes more sense to go to the left anyway, since that’s the side of the house that has the sidewalk to the front.

Steps removed

Steps removed

Once the new wall and stairs are in place, we’ll build some temporary stairs down from the sliding door, since we won’t have the deck for some time. In the mean time we’re going around to the front or climbing in and out, sometimes with the help of a step-ladder. Hopefully the concrete guy will be starting in the next few days and we can get the temporary stairs built in the next few weeks. The plumbers finally started yesterday and I met with some tuck pointers that should be able to fix up the basement door and window openings in a couple of weeks, and last night we picked up the new exterior door for the basement, so we’re making progress on a few fronts.

Mechanical Room Layout

Original plan

Original plan

The location, dimensions, and layout of our basement mechanical room have shifted as we developed our plans and then those plans ran up against reality. The original plan our architect developed put the mechanical room in the back North corner of the basement, but this resulted in a twisting hallway and a lot of wasted space.

Early revision

Early revision

I started playing around with the design, moving the mechanical room over to the South corner, but while this plan worked and gave us a lot of room for storage, and kept the front area of the basement big, it didn’t work when it came time to install the boiler and water heater. Since we didn’t have the interior walls built when we needed to start installing equipment, everything needed to be on an exterior wall. The boiler and all the radiant equipment didn’t fit on one side of the window, which meant we needed to change the plan to make everything fit.

Later revision

Later revision

With everything shifted toward the front, the back room gets a lot bigger. The issue with this plan was that despite the back room being big, there was almost no wall space for storage shelves. The back corner has an electrical panel, and the top (North) wall is effectively the hallway because the door is along the wall. There’d be room for maybe two shelves. So I shifted the bathroom and door back from the top wall so that there would be more room.

Nearly final

Nearly final

This plan took some space from the mechanical room, but everything else seemed to work great. It could fit three shelves along the North wall, moved the utility sink from the laundry so we’d have a temporary kitchen when we moved to the basement, and I was sure this would be the final plan. Once again, reality intervened. When I installed the panel in the mechanical room I aligned the front edge with a floor joist so that the wall between the front room and bathroom/mechanical room could be along a floor joist. As a result it moved toward the front by almost a foot. Bath tubs are sold in convenient five-foot or six-foot sizes. Since the back wall aligned with the steel column, it meant that the nice simple rectangle for the bathroom needed to be adjusted to accommodate a five foot bath tub in an almost six foot wide room.

Final revision

Final revision

With this adjustment made I had to play a mental game of Tetris with the various items in the mechanical room, namely the ejector pit, sump pit, and hot water heater. The challenge is the existing sewer pipe under the ground prevents the sump or ejector from going in certain spots, the trench for the weeping system imposes additional challenges, the water heater already has piping, venting, and gas lines to its current location, and at the same time I need to allow sufficient clearance to get in and out of the room, including not just servicing but replacing equipment in the hopefully very distant future. I think I’ve accounted for everything and worked out the final locations so I can start digging some holes. The plumbers are supposed to start this week, so whatever plan is in place is the last plan we’ll have.

Basement Updates

I haven’t posted in a while because I’ve been trying to complete something before making a post about it, but I haven’t finished anything other than leveling the subsoil, which I already made a post about when I was a third of the way done with it. I didn’t want to write another post just to say I’d finished, especially since flattening dirt isn’t particularly interesting, even if it is a lot of work. Instead there are about five different things in progress, all basement related, so I’ll give a run down on where we are and what we’re trying to get done.

First off: the plumbers. We’ve signed our contract, paid the deposit, permits are being pulled and/or updated, and once that’s done they can get started. Rather than dig up the existing clay sewer pipe they are going to re-line it, a process where they run a scope, clean out the pipe with water jets, then shove an inflatable sock down it all the way to the city sewer main. They inflate it and then squeeze an epoxy resin around the sock, which not only creates a whole new pipe within the existing one, it fills any cracks or holes at the same time. The result is a brand new sewer line without any digging, plus it will actually be a larger 6″ diameter pipe than it would be if it had been if we had redone it in cast iron. The sewer line will be an “overhead system” meaning it will go up to collect the drains from the first and second floor, but the basement drains will go to an ejector pit which then pumps up to the level of the first floor before entering the drain. That prevents sewer backups from flooding the basement.

Next, the plumbers will need to dig a hole in the basement and a couple pits out at the street so they can horizontally bore a new copper supply line and disconnect the old lead line. Once that enters the basement at the front there will be a new water meter and an overhead copper line running along the beam back to the mechanical room. Finally, they will be canceling our old catch basin in the back yard and running the rough plumbing for the basement bathroom. The process should take about four or five weeks, depending on permits and inspections.

While that’s going on I’ve been working on the interior weeping system (aka drain tile). I’ve dug a trench around most of the basement that will connect to a sump basin. I picked up a large 24″ x 36″ crock that’s about twice what’s required by code. I’m still researching sump pumps to put into it. For now that will tie into our sewer system, as Chicago code allows combined storm and sewer, but once we’ve redone the back yard I plan to route this into a rain garden along with the downspouts and the drainage for the walkway along the side of the house.

I’ve talked to our concrete guy about getting the back steps redone while it’s still warm enough out. Our plans call for the exterior basement steps to go to the South rather than straight out or to the North as they do now, so we need them to knock out the existing retaining walls and put in a new one. The plumbers will install  an area drain at the bottom landing that connects to the weeping system. Hopefully he’ll be out this week so we can get that process rolling. We unfortunately had to fill in the pit we had dug for the steps with all the excess dirt from leveling the basement and digging the trench.

Lastly, I tried replacing the rest of the basement windows yesterday but discovered the brick around the windows and the sills are in worse shape than I had hoped, so I called our tuckpointers. We’ll have them replace the sills and clean up the window and door openings so we can get the rest of the new windows installed. I also ordered our new back door, since it will take a few weeks to get it in.

So despite not being good about updating the blog, we are keeping busy with the house. As we finish any of these projects I’ll write posts about them individually. The weather is getting much cooler as Fall sets in, so we need to get a lot done in the next several weeks!

Basement Dig Out – Part Forever

My last basement dig out post was June 3rd. With the dumpsters and excavator gone we stalled out and decided just to hire the rest out. The concrete contractors we talked to gave us some very reasonable quotes and we were just waiting for the plumbers to get back to us. We finally got a couple plumbing quotes, but they’re really, really expensive.

We’re basically looking for three things from the plumbers: (1) replace the old clay sewer line under the basement floor with an overhead system plus rough-in for the basement bathroom and floor drains to an ejector pit, (2) replace the old lead water service with a new copper line, and (3) install an interior weeping system (aka drain tile) with a sump pit. The new water line in particular involves either excavating pits and horizontal boring or a trench across the yard and the street, so it’s the biggest line item, but the sewer work is pretty pricey too.

We’re going to try and get another couple quotes in hopes of a less expensive option, but time is getting short to get this work done before the cold weather sets in. In the mean time, we’re going to tackle the weeping system ourselves. While it’s the least expensive item on the list, it’s the only one we can realistically do. Even though it  won’t bring the plumbing costs down by a lot, we’ve got to do everything we can if we want to move forward.

Before we can put in the weeping system we need to level the subsoil in the basement. When we dug out the basement with the mini-excavator, our limited experience meant the end result wasn’t what you’d call perfectly smooth. Because it’s all clay, making it flat is extremely labor intensive. We’d held off leveling it until we’d talked to the plumbers because we weren’t sure if they were going to have to dig up the existing sewer and water lines. Now we know that’s not the case and we can get started. They’ll only need to dig a hole in the front corner, and over by the soil stack.

Not level

Not level

The first step was to dig out the corners where we couldn’t get the excavator in close, then go around with a pressure washer and clean up the stone footings. Once everything was cleaned up I used the laser level to measure how close to level the subsoil is. I started working from the front bay window toward the back of the house, focusing on one four foot square at a time. I quickly discovered there’s a gradient of clay consistency from one side of the house to the other, requiring different techniques to level out.

Level line

Level line

On the North side of the house the hard-packed clay is the consistency of old, dried fudge. It’s so dense you can’t slice a shovel through it and I have to use the mattock to chip it away. As I move to the other side, it gets gradually softer, which is why a lot of that side is actually dug too deep. So, I take all the clay shavings from the one side and dump them on the other, then use a block of wood and a hand-held sledge hammer to pound it flat. I thought about using a plate compactor or a lawn roller, but everywhere I need to compact the clay it’s sticky and would make a huge mess. As much as I don’t want to do it all by hand, it’s probably the only way. I drew a line on both the shovel and my block of wood to check my progress as I went, as well as a longer board that I could use to check larger areas. Basically, everything needs to be 6″ below the laser line.

Progress is very slow. I often find myself adding up square footage in my head and breaking it down into percentages, since while the digging is physically hard and time consuming, it’s also mind numbing. Each 4×4 section is averaging me nearly half an hour. I’ve only done about 300 square feet so far, to the back of the first column footing, but just that has been a huge pain over several days.

I’m planning to get the leveling finished over the long weekend, but there’s a lot more work to the weeping system. My hope is that by doing this portion ourselves, we can save enough money to still move forward with the basement this year. After getting excited about our reinvigorated timeline, I don’t want to get derailed out of the gate.

Basement Side Bay Windows

Original window

We bought our new basement windows over six months ago, and I’m finally getting around to installing them. When we bought the house, one of the very first orders of business was securing the exterior from rats, weather, and intruders. The two windows on either side of the bay in the basement were in terrible shape so we just boarded them up and they stayed that way until we had the tuckpointing done. We had the tuckpointers put in new concrete sills on the bay windows, but on the two sides we still needed to replace the lintels and add a tier of bricks to either side.

Dean came over and helped me mortar in the bricks on either side of the windows and position the new lintel. There’s no brick above the lintels, since the windows are at the top of the basement wall, but there is a floor joist that rests on the middle of the window, so I wanted to make sure it was supported by more than the buck.

Dean brick laying

Dean brick laying

Because we added the bricks, the already not 100% square opening was made less so, so when it came time to build the bucks we wound doing a lot of careful measuring and shimming. The finished openings were a bit smaller than anticipated and I had to make the sides of the bucks out of 1″ instead of 2″ pressure treated lumber. I secured it to the brick with Tapcons and filled the gaps with backer rod, sill insulation, and canned spray foam.

The windows are Newtec R-5 triple pane. We chose casements for the sides so we can direct airflow into the basement. The center window will be a fixed picture window. They’re vinyl, unlike the fiberglass windows we put in the first floor, but they perform better and cost a lot less. The basement windows aren’t especially large, so I’m not too concerned with the vinyl expanding and separating from the glass.

After Dean helped me install the first buck and window last weekend, I installed the one on the other side of the bay on Wednesday and got everything caulked and sealed. I missed one spot on the right window with the Great Stuff that I’ll catch when I’m doing the next one. For now we’re not installing the middle bay window so the opening can be used by plumbers and concrete guys. I’m planning to switch to 2×8 bucks instead of 2×6 for the remaining windows so that they will be flush with the inside of the wall, which will simplify framing and trim later.