From the outset, the goal of the bump-out removal plan was to accomplish the removal with a minimum of time spent on extension ladders. That was largely intended to make the process safer, but honestly, the wall removal didn’t always feel completely safe. For this step of the project, Sarah’s dad, Mike, came and helped. I spent the most of the morning getting the remainder of the siding off, as well as the one small side wall. When that was finally done things got moving, since the sheathing was pretty quick. The tricky part was the framing. From all the rain, the already heavy rough-cut, full-dimensional lumber was even heavier. To keep weight under control, I cut bigger pieces down rather than pulling down larger boards whole.
Unfortunately, the relatively tight quarters and limited means of access meant that Mike couldn’t actually get onto the bump-out with me, so I was on my own for some of the trickier bits of framing removal, then I could hand it to him through the open section. Once again, I’m kicking myself for the way I put the sheathing on the new wall section, since I could have made a convenient doorway that was far easier to use if I’d stopped and thought about it. As it was, I’d get a piece loose and then hand it through the opening to Mike, who was standing on the inside. Eventually we got the walls down, and fortunately no one was seriously injured.
The next step was to patch up the remaining bits of roof sheathing that had to wait until the side walls were gone. This we did the smarter way, by first putting in sheathing and tar paper, then shingles, rather than trying to fit already shingled sections into the roof. Mike was able to scavenge all the parts from the old roof and while it still looks terrible, it appears to be water tight. We plan to replace to whole roof in the not-too-distant future, so it doesn’t need to last all that long.
June 1, 2017 at 9:09 am
Nice progress!