Author: Matt

Footings and More Radiant

The Concrete guys poured the back porch footings, including the rebar. I was in meetings all day and couldn’t keep an eye on things, but when I went out there after a bit they left I noticed that the footings at the bottom of the stairs were six or eight inches above grade. Since the concrete was still wet, I grabbed a trowel and a level and scooped the sonotubes down to where they should be, level with grade. I also shoveled out the small section of sidewalk they had thoughtfully poured with extra, despite me asking them not to since we have pavers for that area. It’s been a couple of weeks and the dumpster is still in the back yard. Now he says tomorrow?

New footings

There’s been some further back and forth with the architect, expeditor, GC, porch contractor, and myself, trying to get permit moved along. I’m not sure how much longer it will drag out. On a positive note, I got an email today from the cabinet maker that price changes go into effect on January 1, but while most prices are going up, cherry wood prices are actually going down, so we may actually save money by waiting. I’m not feeling like we’ll need those cabinets before mid-February at our current rate of “progress”.

This past weekend I got to work on the radiator lines in the attic. I mounted the manifold in a closet and got the supply and return pex tubing installed to each of the radiator locations. There’s a bit to do yet. I installed framing in front that we’ll eventually mount the radiator to, but I still have to do the same in back. I also need to terminate all the lines with the stainless steel pipe I bought and then cap them so I can do a pressure test. I’m still waiting for some more parts to arrive before I can do the mechanical room work, but there’s plenty to do before then.

Meanwhile, I’m hoping that the GC can at least install the new house wrap, called “Blue Skin”, since I think some of the penetrations we’re waiting on will actually need to be set up after it’s installed because of the exterior insulation panels. He says tomorrow or Friday, which I take to mean Friday at the earliest.

They’re also going to ‘reset’ all the windows. I think I mentioned previously that all of the windows (except for the basement), which I installed using clips provided by the distributor, are installed incorrectly because the clips are actually for a completely different brand of window, which explains why they were such a pain to use. They are going to remove the clips, foam, and wrap around the windows and put them back in, but proud an inch or whatever so they’ll be flush with the exterior trim.

So! The next update should have some exciting progress.

New Roof, Same Crazy House

New roof

Just two short years after we got the original quote, we have our new roof. Last week Wednesday the crew showed up and got to work. It took three days, but the whole thing is done. It was windy all weekend, so I haven’t gotten up on a ladder to see for myself, but we can see the porch and the the bay window peak from inside and they look good. Nothing blew off the roof in the wind, and everything inside stayed dry, so I’m calling that a win. We’ve been emptying a bucket every time it rained ever since I cut the hole in the roof for the kitchen exhaust.

Ripped house wrap

On the downside, the old shingles falling during demo ripped up our house wrap and it was flapping all Saturday night so bad we couldn’t sleep. I got it taped down yesterday after things dried out a bit. We’d really like to get the new house wrap, exterior insulation, and siding, but we’re waiting on the electrician to put in the exterior boxes. He’s in turn waiting on permit, permit is waiting on our architect, who is waiting on the permit expeditor, who is waiting on the architect.

The concrete guy got a dumpster dropped off in the back yard today to clear out some of the debris and get the footings poured. That may be as soon as tomorrow. I just need to make sure he actually puts in the rebar.

I never heard back from the radiant company, so rather than chase them down I went ahead and figured out everything we need in the mechanical room to finish the system and got that on order. It’ll be a bit of a project to reconfigure the system for the additional loops, but I think I’ve worked out everything I need to do it. At this point the only thing left to buy for the entire radiant system is some odds and ends for the radiators in the attic.

Basement life

The other big activity this weekend was moving the chest freezer into the basement. It’s been on the first floor ever since we moved down here, but we’ve got to get everything cleared out upstairs. Sarah and the kids got everything emptied out into coolers and laundry baskets, then I chipped the ice out, put it on the hand truck, and with Sarah’s help we got it into the basement.

Just like I did for the refrigerator, we put it up on a block of wood (part of the old wood beam that we replaced) so that it can sit on top of the curb against the outside wall. Even with packing our storage unit to the top, our basement shelves are piled high at this point. We’re running out of room everywhere; clearly we have too much stuff. I need to run some more things to storage and hopefully find a spot for it all.

Sample door

We also got our sample door for our kitchen cabinets. We’re pretty excited about it. The whole world seems to have gone to white, painted, and/or modern kitchens, but we’re sticking with traditional stained cabinets. I’m tempted to switch to a simpler profile and save some money, but I’m pretty sure we’ll wind up going with this.

Movement

I’ve continued to chip away at my list, getting the drain stubs squared away, more acoustical stud tape installed, the first floor beam padded out with 1x4s so we can drywall over the brackets, and a handful of other odds and ends finished.

It looks like permit has progressed. I haven’t heard from anyone, but I looked it up on the city’s portal and can see several new entries, so that’s promising. We still don’t have a new roof, but we’ve been told “Monday at the latest” so maybe that will materialize.

Most significantly, the concrete crew showed up to dig the porch footings. This was the first time someone we paid has actually come and worked on our house since early last year, so it was pretty exciting. They came last Thursday, and then returned Monday and yesterday. All of the holes are dug, though there are some obstructions to contend with. Of course the holes happen to be where we used to have a concrete wall for the stairs out of the basement, and where the catch basin used to be, and the bottom of the stairs is where we’d run the pipe for our drainage project.

All of the concrete sawing, jackhammering, sledge hammering, and digging was a preview of what we’re in for if we’re here in the basement during construction. It’s not promising, but we’ll see how the roof goes. The kids were also mostly stuck inside, which they’re not used to. The back yard is now full of not only holes but big piles of dirt, and both are enticing playthings to kids.

The concrete company was one of the items we paid out of pocket rather than through the loan, since the quote we’d gotten from the builder was really high. I’m somehow not surprised that’s the actual work that’s been started.

I’m not sure when the concrete guys plan to come back and assemble rebar and do the pour, but I can almost guarantee it will be the same day the builder wants to do the roof. If either of them are upset about this, I intend to point out that they didn’t communicate a date to me in advance which makes it difficult to coordinate.

Radiant Dreams

The architect sent something back to the permit expeditor, so maybe that’s moving forward? I’m not sure. Something else to follow up on. We don’t have a new roof yet, but we still have a round 8″ hole in the roof that lets in the rain. Apparently the “Estate Gray” color is out of stock everywhere for the rest of the year. Instead we’re getting Onyx Black, which I don’t like as much, but hopefully at at least they can install it. I suspected when we had beautiful weather at the beginning of the month that it meant we weren’t getting our roof, and so it was. The weather has turned to cold and rainy, and even though we settled on the “in stock” color a week ago, no word yet as to when they’ll be putting it on.

I pinged the concrete guy since two weeks had turned to three. He said the end of this week as long as it didn’t rain. Well the end of the week is here, and it’s been rainy. Next week temperatures are dropping into the thirties; not great for pouring concrete. I haven’t heard back from him yet about a new date.

I asked the radiant company if there was any way to lower the cost (partially since they had originally quoted me much lower, suggesting such a thing was possible) and they never responded. I considered just putting down a half inch of plywood and heating with minisplits, but this is a feature of the house we’re really set on and don’t want to give up. If I had it to do over, I might have skipped it, but we’re committed at this point.

Instead, I started measuring, whiteboarding, planning, spreadsheeting, and SketchUping (I promise at least some of these are real verbs). The result is a complete hydronic radiant floor panel plan of equally-balanced loops each under the maximum length that all connect back to a central manifold.

First Floor Radiant Plan

There are apparently tools to help you do this, but I didn’t have them, so I made some formulas in Google Sheets, I fired up SketchUp, and I worked it out. It’s not the most elegant design, but it keeps the loops all the same size, which is the real trick. Since each floor is one temperature zone, it doesn’t especially matter if the loops are divided into discrete areas of the floor, just that they are the same size so that the manifold will flow evenly throughout.

After I worked out the first floor, the second floor came together more quickly, even though it’s quite a bit more complicated, since there are more rooms and less open space. The first step was to cover the house in rectangles that had a dimension divisible by 7″, the width of one panel. Cutting them down is certainly possible, but it will go much faster if I only do length cuts with the chop saw. The total square footage (actually I worked in square inchage) is divided to an ideal size for each loop. Then I come up with a layout plan that works. I had to work out ways to “borrow” from one loop to make another the right size, and then work back through the remaining adjacent loops to even everything out. If I came across something that changed the area to cover, everything had to be recalibrated. It was a bit of a pain.

Second Floor Radiant

After a few days I had all the loops designed. The next step was to measure up the total length of the straight and return sections to come up with exactly how much I needed to buy. I used another spreadsheet formula to confirm my panel coverage matched my area and saved myself a ton of errors. After finding the best deal online, paying the equivalent of a decent used compact car, and clicking the order button, I had a glass of scotch and wondered —not for the first time— about my life choices.

So many boxes!

Just a couple of days later, I got a delivery notification and went out front to find the above box collection in the front yard. I’m not sure why they didn’t ring the doorbell, but as each box weighs about 60 lbs and it was a short enough time, none of it walked off (to my knowledge). We got it all inside and I’m now in the process of carting it up to the attic, one of the few places we’re not putting in-floor radiant heat and it hopefully won’t be in the way.

I emailed the radiant contractor (again) this time asking for a revised quote where they just install the pumps and controls. I have a miter saw, a collated screw gun, and the ability to follow directions, so I plan to take some time off work and put this stuff in myself. In theory, we’ll save a chunk of money in the process. If I’m lucky, it may all wind up costing around what they wanted to charge in the first place. We’ll see if they respond this time.

My preference is not to install the floor panels until the drywall is in to ensure it doesn’t get damaged, so that will be a while, especially at the pace things are going. I’ll still need the manifolds installed and the pex run through the walls, but I think I can manage that in a weekend or two. Wish me luck!

Contractor Struggles

This is starting to feel like a theme. I mentioned last time that I had to put down a bunch of money for HVAC (specifically the hydronic radiant heat) and they were coming out to do the layout. Well, the good news is that I got a refund of all that money, but the bad news is that’s because they ‘underbid’ and can’t do it for what they said because material costs are so high. Apparently there was a misunderstanding of what they needed to do. They gave me a new quote for about 50% more, so now I’m trying to figure out what to do.

Meanwhile, we got kicked back from Zoning a second time and I’m probably going to have to nag the architect to do his job again. I haven’t called him yet; I keep clinging to the hope that he’ll actually respond to email.

There’s more back and forth with paperwork for the initial draw for the loan. I needed to print, sign, scan, and email back more documents. I haven’t heard from the concrete guy that was supposed to be out this week to do the porch footings. I haven’t heard back from the other HVAC guy about the air conditioning. I had questions for him about the outdoor condensers and wall penetrations.

All in all, the only work that’s been done is what I did. I started putting up sound insulating stud and joist tape in interior walls and ceiling of the bedrooms. This wasn’t cheap, but the benefits of better sound proofing are obvious, from our current reality of looping Frozen 2 and Super Smash Bros Ultimate songs or us wanting to watch a movie after the kids go to bed to a future where one or both play musical instruments, this will pay quality of life dividends.

Derek’s bedroom with sound insulating joist and stud tape

The tape is one of three components to our interior sound proofing strategy, along with two layers of 5/8″ drywall on the ceilings (separated by sound glue) and Roxul mineral wool insulation in the interior stud bays.

I still have a long way to go on this project, but Derek’s bedroom is done, Emily’s is next, and from there I’ll do our bedroom, the bathrooms, and the attic bedrooms. We’re not putting this on exterior walls. I figure between the closed cell foam in the stud bays and the 2″ of rigid foam on the outside of the sheathing, we should be in pretty good shape already.