Basement Dig Out – Part Forever

My last basement dig out post was June 3rd. With the dumpsters and excavator gone we stalled out and decided just to hire the rest out. The concrete contractors we talked to gave us some very reasonable quotes and we were just waiting for the plumbers to get back to us. We finally got a couple plumbing quotes, but they’re really, really expensive.

We’re basically looking for three things from the plumbers: (1) replace the old clay sewer line under the basement floor with an overhead system plus rough-in for the basement bathroom and floor drains to an ejector pit, (2) replace the old lead water service with a new copper line, and (3) install an interior weeping system (aka drain tile) with a sump pit. The new water line in particular involves either excavating pits and horizontal boring or a trench across the yard and the street, so it’s the biggest line item, but the sewer work is pretty pricey too.

We’re going to try and get another couple quotes in hopes of a less expensive option, but time is getting short to get this work done before the cold weather sets in. In the mean time, we’re going to tackle the weeping system ourselves. While it’s the least expensive item on the list, it’s the only one we can realistically do. Even though it  won’t bring the plumbing costs down by a lot, we’ve got to do everything we can if we want to move forward.

Before we can put in the weeping system we need to level the subsoil in the basement. When we dug out the basement with the mini-excavator, our limited experience meant the end result wasn’t what you’d call perfectly smooth. Because it’s all clay, making it flat is extremely labor intensive. We’d held off leveling it until we’d talked to the plumbers because we weren’t sure if they were going to have to dig up the existing sewer and water lines. Now we know that’s not the case and we can get started. They’ll only need to dig a hole in the front corner, and over by the soil stack.

Not level

Not level

The first step was to dig out the corners where we couldn’t get the excavator in close, then go around with a pressure washer and clean up the stone footings. Once everything was cleaned up I used the laser level to measure how close to level the subsoil is. I started working from the front bay window toward the back of the house, focusing on one four foot square at a time. I quickly discovered there’s a gradient of clay consistency from one side of the house to the other, requiring different techniques to level out.

Level line

Level line

On the North side of the house the hard-packed clay is the consistency of old, dried fudge. It’s so dense you can’t slice a shovel through it and I have to use the mattock to chip it away. As I move to the other side, it gets gradually softer, which is why a lot of that side is actually dug too deep. So, I take all the clay shavings from the one side and dump them on the other, then use a block of wood and a hand-held sledge hammer to pound it flat. I thought about using a plate compactor or a lawn roller, but everywhere I need to compact the clay it’s sticky and would make a huge mess. As much as I don’t want to do it all by hand, it’s probably the only way. I drew a line on both the shovel and my block of wood to check my progress as I went, as well as a longer board that I could use to check larger areas. Basically, everything needs to be 6″ below the laser line.

Progress is very slow. I often find myself adding up square footage in my head and breaking it down into percentages, since while the digging is physically hard and time consuming, it’s also mind numbing. Each 4×4 section is averaging me nearly half an hour. I’ve only done about 300 square feet so far, to the back of the first column footing, but just that has been a huge pain over several days.

I’m planning to get the leveling finished over the long weekend, but there’s a lot more work to the weeping system. My hope is that by doing this portion ourselves, we can save enough money to still move forward with the basement this year. After getting excited about our reinvigorated timeline, I don’t want to get derailed out of the gate.

Basement Dig Out – Part 3

Sarah using the digger

Sarah using the digger

I’ll be honest; I’m not sure how many “parts” to the dig out there are, but this is Part 3. It kind of feels like it’ll go on forever. We filled our fifth heavy debris dumpster in a row and took back the mini-excavator. I’d like to say that means we’re done, but instead I’m saying that “principle excavation” is complete, which is just another way of saying that we’re not done. What remains to do is finish clearing the dirt from the footings, remove a few piles of loose dirt including the dirt ramp we used to get the digger out the back door, and level everything, probably by renting one of those heavy rollers you fill with water. The bottom line is there’s more than a few wheelbarrows of dirt yet to haul out, and a lot more work to do.

Digging for new back steps

Digging for new back steps

The last thing we used the digger for was to excavate a pit behind the house. This is where the new outside basement steps will go. Having the steps go up to the left makes more sense since it’s toward the sidewalk that runs along the side of the house and to the currently nonexistent garage, but it requires some reconfiguration, by which I mean busting out the existing concrete retaining walls and stairs and then putting in a new one. With the steps going to the left, we can eventually put a deck on the right side of the house.

In addition to the final clearing and leveling, we also need to clean up the inside edge of the footings so that it’s even enough to finish the walls down the road. Exactly how we do that “clean up” remains to be seen, but it’s stone, so probably hammer and chisel, concrete saw, and angle grinder. Of course after everything is nice  and clean and level we have to dig trenches for the plumbing and weeping system, so we’ll be busy for a while yet.

Because we have to take out the concrete walls and there’s undoubtedly more dirt to clear for the stairs, there’s a strong likelihood we’ll need yet another dumpster in the not-too-distant future. Also, just a heads up to anyone planning an extended rental from Home Depot: a “month” is four weeks, so if you bring it back in thirty days it costs extra.

Basement Dig Out – Part 2

Ramp to basement

Ramp to basement

I’ve got this great new workout you should try; it’s called “pushing wheelbarrows full of clay up a steep ramp”. In the last two weeks we’ve filled two 10-yard heavy debris dumpsters, emphasis on the heavy. Tomorrow they swap the full dumpster for an empty one and it starts again, so this is basically our day off. We’re getting one per week and I expect that to continue for the next couple weeks.

Second dumpster filled

Second dumpster filled

Our original wheel barrow was old when we got it and was not up to the rigors of this project.  The bucket tore loose from the frame and we set it aside. Sarah’s dad lent us his wheelbarrow, but it’s looking a little crooked these days. Sarah bought two new wheelbarrows, and between the three we’ve been putting them to use. I hauled 30 loads in two hours Saturday evening. I’d guess each dumpster is about 150 loads, since we can only fill the wheelbarrows about half-full and still push them up the basement ramp. The ramps are working well, though the one up from the basement is the tough one, especially when it gets slick from the rain and mud. The ramp I built to get up to the top of the dumpsters is great, though. That was time well spent.

Digger and wheelbarrows

Digger and wheelbarrows

The digger (mini excavator) has proven its worth too. Every time we grab a shovel to manually dig around the footings we’re given a taste of what the task would have been like without it, and it’s just awful. Digging with the backhoe on the other hand is a breeze. Hauling up bucketfuls of heavy clay, the hardest part is dropping clods into the wheelbarrows without knocking them over (especially the crooked one) and not digging too deep. I used my laser level to confirm the footings are pretty consistent in height, so we just need to dig even with the bottom of them, about 14 inches total.

Excavation

Excavation

Looking forward, we’ve gotten about a third of the dirt removed. With the dumpster we get tomorrow we can get most of the next third removed. That means it will be time to move the water heater and the laundry upstairs so we can pull up the last section of concrete floor. I’m taking off some time from work next week to get that done as well as level what we’ve dug so far. Our goal is to finish with the digger by the weekend after Memorial Day, which includes digging out the new back steps. May’s looking pretty busy!

Basement Dig Out – Part 1

Loading dumpster

Loading dumpster

It’s time to start digging out the basement! We got the first heavy debris dumpster in and last week I took out the concrete back steps leading out of the basement with a sledge and the rotary hammer so we can make a ramp. I used the concrete saw to cut out a section of patio at the top of the stairs to make the ramp more gradual, then put in a section of shingled plywood from the garage roof so we could start bringing wheel barrows up.

We got the leftover concrete that didn’t fit in the previous dumpster loaded, along with the pile of bricks and dirt that I’d pulled up by hand. Just that was enough to fill the dumpster to the point that we had to close the door. Then we started using the ramp and platform I built to dump full wheelbarrows into the dumpster.

Mini excavator

Mini excavator

Saturday I picked up the tool that will help make the dig out just a bit easier: a mini excavator. After a quick review of a Youtube video for a similar model, we got the excavator into the basement (I wound up having to take the door jam off) and started digging. The bottleneck is definitely the wheelbarrows. The excavator can fill a wheelbarrow in two buckets, so it took some practice before we worked out a solid system for working efficiently. About the time we’d worked it out, the first dumpster was full and we had to stop.

While we wait for the next dumpster I’ll start clearing out the footings along the wall and get our depth figured out. Up to this point we’ve been winging it, and we don’t want to go too deep! Using the excavator is fun, but I’m still sore from pushing all the wheel barrows of dirt up the ramp. We’re expecting to have three or four dumpsters all told, so this process will probably eat up the better part of a month.

Back Yard Cleanup and Ramp

Starting to fill

Starting to fill

Following our back porch and garage demo, Sarah cleared a path in the back yard and last Friday the dumpster was delivered for all the debris. Unfortunately, even with careful loading and help from Dean we couldn’t fit everything in. Tuesday they swapped the full 30 yard dumpster for an empty 15 yard so we could get the rest of the debris cleared out.

Filled to the top

Filled to the top and getting picked up

Before loading the second dumpster, I harvested some of the materials to build a ramp. Our previous experience with heavy debris dumpsters has made it clear that we need a better way to dump full wheelbarrows of concrete and dirt. For the first half of loading, the door of the dumpster is open and it’s pretty straightforward, but after the dumpster starts to fill and the door is closed, it’s not so simple. Previously we wound up using buckets or in the case of concrete, unloading by hand. But building a ramp makes the whole process much easier, and since we’re going to have at least three full dumpsters of heavy clay, it’s worth doing.

Ramp design

Ramp design

After a bit of brainstorming the simplest way to make a ramp that would stand up to load after load of heavy wheelbarrows, I settled on a design and drew it in Sketchup, using the measurements of all the pieces from my drawing to make a part list. I picked out 2x6s of the appropriate size from the garage pile and cut them per plan and then assembled the thing. It actually worked out really well and I got the whole thing done in a couple hours.

Completed Ramp (also Derek)

Completed Ramp (also Derek)

The second half of the ramp is a level platform to make it easier to turn the wheel barrow and dump it in. I didn’t bother with Sketchup because it was all right angles. I just cut a stack of boards and then screwed it together. The tops of the ramp and platform are sections of roof from the garage. The idea is that the shingles will make it easier to get traction with the wheel barrow, especially since it will probably get pretty muddy. We also kept a couple of roof sections for the dirt ramp we’ll have into the basement once I remove the back steps.

Ramp and platform

Ramp and platform

We got the second dumpster filled and even had enough room left for Dean and Siobhan to bring over a couple of carloads of junk that’s been accumulating in their garage. I didn’t get a picture of it full, but imagine a full dumpster and there you go.

First dirt dumpster

The new dirt dumpster was just dropped off and we’ve got some work ahead of us. You can see how the ramp will help with the loading once the door is closed. Things are about to get busy!