Category: Garage

Garage Build

Ok, the short version is we have a garage now. I’m going to assume that if you’re reading this and not just looking at the photos, that you want the play-by-play. Once again, I’ve done a poor job of keeping up with blogging, but I’m trying again.

With Sarah and I temporarily moving the neighbor’s fence back a couple of feet the length of the garage, we had a few conversations with them about why that was happening, but they were concerned about the garage being up to the property line. Their contractor had told them that was against code. I showed them our plan and permit and explained that applied to frame garages, and the reason we were building a masonry garage was so that we could build up to the line.

Work went quickly at first. The spread footings were poured two days after my last post. Forms and rebar were in two days later, and the footings were poured the day after that. The forms came off the next day, gravel was spread and block was delivered. If you’re not keeping track, this is July 15th. By the 18th, the walls were up to ceiling height, steel was installed over the garage door opening, and the roof framing was in. The contractor had told us they estimated six weeks, which seemed incredibly optimistic, but so far, so good.

At this point, Sarah and I went on a trip for our fifteenth anniversary. While we were enjoying a tropical paradise, I got a voicemail from the contractor that the city had stopped work because the permit was bad and slapped a big ‘ol orange sign on the front of our house. When we got back a couple of days later, I found that the 311 complaint number wasn’t valid and the phone number of the inspector was disconnected. However, the email address of their supervisor was correct so I contacted him. He responded that the permit actually was valid and we could resume work and take down the sign, which I did. He said he’d pull back the violation so it didn’t go to a hearing. With that settled, and strong indications of who had complained, work started back up again.

Within a week, now the end of July, the parapet wall was done and a few days after that the exterior was painted. Several days later, the roof went on. About here, things started happening less quickly. The roof and flashing were done by the 22nd of August, and the pad was poured the following day. At this point we figured we needed doors, windows, and some cleanup and we could call it done. Emailing with the contractor, we found he hadn’t ordered the side doors yet. His price was much higher than quoted, so we decided to shop for ourselves, which prompted me to go double check the measurements.

To fix this, obviously weren’t going to take out the whole slab, so instead they came back with a telehandler, cut out a course of cinder blocks, lifted the whole steel beam up, and made all of the door openings taller. I was impressed how they pulled this off and in the finished product you’d never know. Masonry was definitely their specialty and they did that part really well.

That’s when we discovered there was an issue. When they put the footings in, they didn’t leave a notch for the rear access door. We pointed that out and they left the door opening and said they would come back and notch the door, which they never did. The slab was poured by a sub that assumed the height was where it was supposed to be and sloped accordingly. As a result, all of the door openings were too short. Our 8′ garage door was less than 91″ and our 80″ access doors (which need an 82.5″ rough opening) were under 80″. I let the contractor know, and the next day his overhead garage door installer showed up and let him know the same thing.

With things dragging, I was anxious to get the neighbors to the North their sidewalk back. The contractors had left a piece of rebar embedded in concrete where their pavers had been and ignored all of requests to fix it. I finally broke the concrete out myself and cut down the pavers to fill back in. With a hose, a little polymeric sand, and a broom, I got it looking like it did before and I reinstalled the gate, which required way more reconstruction than I hoped, but I got it done in the end. Getting out of the other neighbor’s yard required us to build a new fence, which I’ll leave for another post.

Sarah and I picked up the access doors ourselves and dropped them off. They got them installed along with the windows, but left the Great Stuff sticking out everywhere. We had agreed to paint them, but the overhead door went in with bare 2x6s and no flashing. They left the flashing in the back of the garage, so clearly they intended to install it. I wound up painting that too and Sarah and I got a sheet of Hardie trim to clad the 2x6s, but they wound up coming back and putting aluminum flashing on it after all.

Finally parked in the garage! (Before we got the flashing and painted the doors)

Finally, on September 20th, the slab had been curing long enough and the overhead door was installed so we were able to park in the garage. This coincided with street cleaning day, which was convenient. The garage door installer also installed the opener I told them I didn’t want. I wanted a wall-mounted unit, plus at this point there wasn’t power in the garage, since the contractor quoted us way too much to put in an electric charging circuit.

It’s been a dramatic lifestyle improvement to be able to park in the garage. Street parking while it was under construction was a hassle, and before that manually opening and closing the gate to the yard as we came and went was a chore. I’ll go into some details on the electrical, garage door opener, and other details in a future post.

Garage Excavation Prep

After a number of quotes, we bit the bullet and signed on to get the garage built. We made an initial deposit on Friday and they said they’d be in touch Monday to discuss scheduling. Instead, Monday they showed up with an excavator. Unfortunately, even though the concrete demo was done, we weren’t quite ready for them to start.

Monday morning surprise excavator!

Primarily, we needed to get the fences along the sides of the yard removed. We also needed temporary fencing, a porta-john, and while they had asked if we had a survey and we said yes, we actually needed the physical survey markers at the corners of the property. So they wound up leaving and left us to get prepared. Sadly, we also had to take down the swing set I built for the kids during Covid.

Fence panels removed on North side

We started with conversations with the neighbors to either side, getting permission to encroach temporarily on their yards during construction. On the one side, the fence was built during their renovation, but on our side of the property line. That made it our fence, so we just needed to make sure they were ok with closing off their access to the sidewalk along the garage while we removed it. They have a toddler and we want to make sure their yard is secure.

Fence posts removed, temporary fence delivered

On the other side, there’s actually two fences, a chain link on our side and a wooden picket fence on the other. We got permission to relocate the wooden fence about a foot back from the property line as long as it was secure for their dog. We got the porta-john, the temporary fencing was delivered, we got an expedited survey done, and took out the fence.

Chain link fence and stump removed, South fence moved

The fence posts and the tree that had grown in between the two fences were the bigger challenge. We picked up a “farm jack” which was a tool I was previously unfamiliar with but will use anytime we have a post to remove in the future. It lets you ratchet the post straight out of the ground, with or without the concrete footer attached. Sarah and I took out about eight or ten wood and metal fence posts in fairly short order. I wasn’t as lucky with the tree stump. That required some extensive work with a reciprocating saw and long blade, but I managed to get that ripped out of the ground. Sarah and I moved a few sections of the wooden fence on the South side back a foot and made it secure for the dog next door.

With everything removed and prepped and all of the fence debris and landscaping stones cleared away, we let the contractors know they were good to proceed. They showed up the following week on Tuesday and had the footings completely excavated in just a couple of days. They actually cut back the sidewalk on the neighbors side where it was over the property line, so we’ll need to fix their side gate once the walls are up.

Back Yard Concrete Demo

I’m going to skip over all the things that I haven’t kept the blog updated about and go straight into covering various projects. So, I apologize that they won’t be posted in chronological order, since we’ve done a ton of projects since I fell off the posting timeline and the effort involved in getting caught up on everything is a big reason I haven’t bothered.

So, concrete demo. Let’s back up a step. When we bought the house, there was a two car garage in the back (we have an alley). It was probably a 1.5 car garage when it was built but they poured a three foot concrete pad next to the garage and literally moved the wall over, increasing the door size in the process and adding a single car door to the yard (maybe the original door? I don’t know) and extending the roof to reach the wall in its new location. So the garage was in bad shape, none of it was done well, and we tore it down years ago. In addition, the back yard had a concrete patio covering most of the area in back.

In addition to wanting a new garage, we wanted to get rid of the concrete patio. We plan to eventually put in a smaller paver patio. When we started getting quotes on the garage, we asked for removal of the patio concrete at the same time. When we took out the loan to finish the house, we wound up removing the garage because the overall price tag was just too much.

In hindsight, it may have been better to just do it, since the prices have not come down in the subsequent years. The garage quotes were really high and we started looking for any way to bring the price down. One of the ways to do that was demo the concrete ourselves.

So, we got a hand-me-down barely-used electric jackhammer from Sarah’s dad and set to work. As with most of these projects, it was harder and took longer than expected, but three heavy-debris dumpsters later, we’d completely cleared the back yard of concrete. The hardest bits were reinforced with steel mesh, and 4-8 inches thick throughout, with most of the patio being 6 inches thick.

The kids helped too, using the jackhammer (with supervision), hauling concrete chunks, and raking and shoveling the tinier bits. The neighbors did not really appreciate us using the loud jackhammer on and off for a couple months. We tried to limit how long we went and which days to be less annoying, but I’m sure we tried their patience. When we got to the back of the yard, we needed to remove and re-build the fence which was a project in and of itself.

In the end, all this was probably not worth it. If I’d known the patio was six inches thick with re-mesh, I may have just paid to have it done since while it absolutely saved us a couple-few thousands of dollars, it wasn’t so much that it felt truly worth the time and effort.

With the concrete removed, we still have a few steps before we’re ready to build a garage, but I’ll cover that in the next post.