First Floor Framing

It’s Fall now, and we really want to get spray foam insulation installed before winter hits. That means we need all the framing done, as well as rough plumbing and electrical. Fortunately on the first floor we have an open floor plan, so there isn’t all that much framing to do. In addition to a few walls we need to finish the fire blocking and add nailing edges to the corners.

Blocking added to wall

Blocking added to wall

A few months ago, Dean came over and we got most of the fire blocking installed. The fire blocking consists of short pieces of 2×4 fit between the exterior wall studs at the floor, halfway up the wall, and behind the ribbon at the ceiling. They help prevent fire from spreading up the wall cavities, improve structural rigidity, add drywall nailing edges, and they’re required by code. Since we changed our plans, the only framing we need to do is the bathroom walls, the half-wall that divides the kitchen from the living room, and a small triangle of wall along the second run of stairs.

Last week I got the two bathroom walls up. As usual there was random shimming and allowances for our out-of-square house, but I must be learning because everything went pretty smoothly (except when one of the wall sections I had stood up fell over, broke the light, and almost crushed my camera). The walls are nice and straight despite the house and I didn’t have to take it apart to cut mis-measured boards.

Sarah’s dad, Mike, was over on Saturday and together we built the kitchen walls. There’s a short section under the beam connected to a half-wall that divides the kitchen from the living room, with a walkway near the wall. That went fairly smoothly, though we did run into one section by the wall we had to redo to compensate for the non-trueness of the outside wall.

Fire blocking with plugs

Fire blocking with holes and plugs

Sunday Sarah and I spent pretty much the whole day finishing the fire blocking. At the front and back of the house the floor joists run parallel to the wall, so if we’d put solid blocking in it would have closed off a pocket in the wall that couldn’t be spray foamed from below. To get around that I drilled 2″ holes in each piece of blocking so the spray foam installer can fill the pocket, put the little wood plug into the hole, then fill the rest of the wall.

Angled framing

Angled framing

Tuesday evening we framed the triangle of wall by the stairs and installed nailing edges at the corners. Wednesday evening our friend Mike came by with his truck and picked up most of our scrap metal pile in the basement, cutting down the big stuff with his torch. We need to clear all that out so the spray foam installers can get between the joists in the basement. We still have to get the tub and old boiler out, as well as some wiring, but it’s a huge improvement.

Truck loaded with scrap (also Derek)

Mike’s truck loaded with scrap (also Derek)

Yesterday I took care of some furring by the front door to even out the wall. We’ve got calls out to our plumber and electrician to get them lined up and see how soon they can do the work. Local code requires we use licensed contractors for the work, and it will certainly take them a lot less time than it would us. That’s not to say we won’t have anything to do ourselves. We still need to add furring to the ceiling, even up some of the outside walls, install the security system wiring, speaker wiring, and cabling conduit, plus clean out the rest of the basement, not to mention finish up a bunch of odds and ends we haven’t gotten around to. The exciting thing is that once all that’s done and Lester does some prep for the radiant floor heating, not only can we get our spray foam insulation, we can start drywalling. It’s been so long coming that it’s exciting just to think about.

Blocking Preparation

Subfloor installed

Subfloor installed

The subfloor is finally all installed, which means it’s time to look forward to the next project: blocking. Blocking is the process of installing short pieces of framing between the wall studs at the bottom, middle, and top of the wall. This provides structural bracing (since the house tends to sway when there are strong winds), fire code (fire inside the wall takes longer to spread if there is solid wood in its way), and as a nailing edge for drywall. In addition, all along the kitchen wall we’ll install extra blocking to make cabinet installation easier.

Before we can get to work measuring, cutting, and installing blocking, I need to do some wall straightening. Because our house is built from rough sawn lumber, the studs are not exactly the same thickness. The original lath and plaster evened things out in ways that drywall will not, so we need to establish what straight looks like and then plane and shim the studs so that they are even and plumb.

Laser line establishes straight

Laser line establishes straight

I started work along the front of the house, where in addition to the above described challenge we have to allow for the support column in the wall and the front door, which is fairly thick. The column is 3½” thick, so it should sit flush, but the column cap at the top extends back, so the column is proud of the wall by about a half inch. I debated framing it as a visible column, but decided instead to bring the wall flush with it. I will still have to deal with the column cap and bolt at the top, so something will wind up being visible regardless, but that’s a finishing detail I’m not currently worried about. Maybe I’ll use a cornice or something.

Laser line on 6' level

Laser line on 6′ level

I used my laser level to project a plumb line and marked my shim position. I ripped that down on the table saw and then cut an angle off of it so that it would match the inside edge of the bay. After I glued and screwed down the remaining shims I ran my straight edge down the wall and realized that things weren’t quite where they were supposed to be. I wound up cutting thin wafers to shim my shims out so that everything was actually flush.

Shimming progress

Shimming progress

One challenge is that I can’t install the blocking at the bottom of the wall in the front or back of the house until the spray foam is put in, since there is a joist preventing the spray foam from being installed from below, as we’ll do on the sides of the house. I’ll wind up measuring and cutting the pieces, but leaving them loose, since we’ll need to put them in during spray foam installation. I also need to contend with the inside corners of the house, since they aren’t framed with a proper nailing edge. Basically, I have some more work to do before I can start putting the blocking in.

Mechanical Room Panel

We finished the first half of the mechanical room panel last weekend, which includes the water filter and heater and a space the future boiler will occupy. The second half of the panel will hold the manifold, pump, and expansion tank for the radiant heating system. I couldn’t build it until the old water heaters were out which, predictably, required the new water heater.

Before

Before

Tuesday morning, Sarah’s dad Mike and I got the two old water heaters disconnected and moved over to the scrap pile. Then we marked out the location of the studs to attach to the wall. After the door delivery, he and Dean ground the brick wall smooth with angle grinders while I cut the lumber to size. I finished grinding down the wall Wednesday and put up the framing. I put sill gasket behind each stud to prevent moisture from seeping into the wood and attached them with Tapcon screws. I found that in several cases the screws wouldn’t go all the way in, despite using an air compressor and vacuum to remove dust and re-drilling the hole several times.

After

After

I discovered the best solution was to drill the holes as I had been with the rotary hammer, then come back and re-drill the holes with the drill bit that came with the screws. Even though they were both 5/32″, something about the included bit worked better. With everything in place, I came back down after dinner and filled the cavities with spray foam. I just need to cut back any places the foam expanded past the front of the framing and it will be ready for Lester to install the manifold panel.

Spray foamed panel

Spray foamed panel

The only remaining item on my mechanical room preparations (aside from cleaning up the huge mess I’ve made) is to run a short length of EMT conduit from the junction box over to the panel and fish a 15 amp circuit for the radiant system.

Sealing the Deal

We needed to close some of the gaps in the outside walls to prevent critters from coming and going. This meant boarding up a few basement windows, adding a threshold to the main back door, and adding some wire mesh to a few other spots. We have our work cut out for us in the attic, but we haven’t gotten to that yet. For now we’re focusing on the ground level perimeter.

Basement window before

This fusion of plexiglass and incompetence was the laundry room window. I ripped all of it out, but left the original window intact, though it was missing a couple of panes. After tucking the wires into the siding to get them out of the way, I screwed a 2×2 cedar board into the bottom so I had a flat surface on all four sides. Cutting the plywood to fit was a trick because the brick foundation is parged in a stucco-like cement. After a few trims I got it in and screwed it in place. Then I painted it, filled the gaps with spray foam, and when that had set I sealed the edges with an exterior caulk.

Basement window after

The back door had a large gap under it, due in part to the porch sloping to one side and in part to the door being a standard size and the doorway being not. I cut out a clean space using the reciprocating saw and used a two by four, along with some shimming blocks to get it level-ish under the door. This wasn’t meant to be quality work, just create a nice snug fit for the door. We filled underneath with spray foam and painted the whole thing to keep the water out.

Back door threshold

The result wasn’t half-bad. I’m sure it could be better, but ultimately we’ll be tearing the whole enclosed porch down, so I wasn’t about to make it especially pretty. It’s now keeping the elements and the rats outside and making us feel a tad more secure.