Second Floor Demo Partition Walls

I was back upstairs this week, removing the interior walls. I left the center wall for the time being. It’s not really a bearing wall, but it probably helps stabilize things and we’re not ready to start on the structure yet. I’ve got some ideas on how I’m going to tackle subfloor leveling as well as the attic floor upgrade, since it’s all 2x6s right now.

South wall, looking East

I’ve also been working on de-nailing all of the exterior walls, which is a tedious bit of business. I’ve made it about 25% around the perimeter. I was able to remove the remainder of the old gas lines for lighting and the last bits of old supply plumbing, plus a portion of the old drain and vent pipe, but there’s still some work to be done to get the rest out, which means the wet wall can’t be removed quite yet.

North wall, looking East

I’ve accumulated a rather sizeable pile of both lumber to be saved and scrap to be pitched. The lumber, much like the outside walls, needs to be de-nailed. I’m also planning out the next steps, which include closing up the windows on the North wall as well as the back door, and putting in the new drain and vent stack. That requires some forethought to get all of the proper junctions and fittings in place for the eventual toilets, sinks, and tubs that will connect to it.

Basement Tuckpointing

Before tuckpointing

Before tuckpointing

The next step down the road to getting our basement livable is repointing the brick walls. 120 years of water damage, bad patching, paint, and neglect had left the brick in bad shape. Large portions of the walls had been parged with mortar or concrete, which can trap water in the brick rather than allowing it to dry. We started by chipping off the parging. Some of it was so loose and brittle we could snap chunks off with our bare hands, while other sections came off only reluctantly with a hammer and chisel. About the time I got my rotary hammer back from a friend, I decided we just needed to hire out the job to some professional tuck pointers.

After hammer and chisel

After hammer and chisel

We got a couple of quotes, but wound up settling on Tuckpointing Masonry Systems, who Dean had used and recommended. They came in with a crew and after two days of dust and noise, the basement looked amazing. They ground out all of the mortar below grade and completely repointed it. Above grade they knocked out the loose material and spot-tuckpointed where it was needed.

After tuckpointing

After tuckpointing

The other thing we had them do was to rebuild the sills on the front bay windows. The bay windows are taller than the other windows in the basement, extending down to ground level, which makes them susceptible to water coming in. To prevent this, the tuck pointers installed new concrete sills with flashing. The next step is to re-frame the two angled windows in the bay, since they currently don’t have lintels.

Rebuilt bay windows

Rebuilt bay windows